Search Climate Insights Directory
5 results
ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED METALLURGICAL CLUSTER OF THE MUSINA-MAKHADO SPECIAL ECONOMIC ZONE
The Centre for Environmental Rights (CER), representing Earthlife Africa, groundWork, and the Mining and Environmental Justice Community Network of South Africa (MEJCON-SA), submitted a formal objection to the Department of Economic Development Environment and Tourism in Limpopo regarding the Environmental Impact Assessment (EIA) for the Musina-Makhado Special Economic Zone (MMSEZ) metallurgical cluster. The CER argues that the Final Environmental Impact Report (FEIR) contains fatal flaws, including insufficient public participation and missing critical data on water and energy, and asserts that the application should have been refused by the regulatory deadline of 19 May 2021.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
OBJECTIONS TO THE 7 DECEMBER 2020 DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT [REVISION 01] OF THE PROPOSED MUSINA-MAKHADO SPECIAL ECONOMIC ZONE, LOCATED WITHIN THE VHEMBE DISTRICT MUNICIPALITY OF THE LIMPOPO PROVINCE
The Centre for Environmental Rights (CER), representing groundWork, Earthlife Africa, and the Mining and Environmental Justice Community Network of South Africa, submitted formal objections to the Revised Draft Environmental Impact Assessment (EIA) for the proposed Musina-Makhado Special Economic Zone (EMSEZ). The CER argues that the EIA is fatally flawed due to procedural unfairness, inadequate public participation, and significant gaps in specialist studies regarding climate change, water scarcity, air quality, and human health. The document asserts that the project's high negative environmental impacts likely outweigh its projected socio-economic benefits and that an environmental authorisation should be denied.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
REQUEST FOR WRITTEN REASONS: INTEGRATED RESOURCE PLAN FOR ELECTRICITY, 2019
The Centre for Environmental Rights (CER), acting on behalf of groundWork and Earthlife Africa NPC, submitted a formal request to Minister Gwede Mantashe for written reasons regarding the promulgation of the updated Integrated Resource Plan (IRP) for Electricity published on 18 October 2019.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
OBJECTIONS TO THE FINAL SCOPING ASSESSMENT REPORT OF THE PROPOSED MUSINA- MAKHADO SPECIAL ECONOMIC ZONE, LOCATED WITHIN THE VHEMBE DISTRICT MUNICIPALITY OF THE LIMPOPO PROVINCE
The Centre for Environmental Rights (CER), representing groundWork and Earthlife Africa, submitted formal objections on November 1, 2019, to the Final Scoping Assessment Report (FSR) for the proposed Musina-Makhado Special Economic Zone (also known as the Energy Metallurgical Special Economic Zone or EMSEZ). The CER argues that the FSR is fatally flawed due to inadequate public participation, a failure to conduct a Strategic Environmental Assessment (SEA), and the appointment of an incorrect competent authority. The document details severe concerns regarding the project's impact on water scarcity, climate change, air quality, and biodiversity in the Limpopo Province.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
FORMAL REQUEST TO SUBMIT COMMENTS ON THE FINAL SCOPING ASSESSMENT REPORT OF THE PROPOSED MUSINA- MAKHADO SPECIAL ECONOMIC ZONE, LOCATED WITHIN THE VHEMBE DISTRICT MUNICIPALITY OF THE LIMPOPO PROVINCE
The Centre for Environmental Rights (CER), representing groundWork and Earthlife Africa, has formally requested the opportunity to comment on the final scoping assessment report for the proposed Musina-Makhado Special Economic Zone (SEZ). The CER objects to the adequacy of the public participation process and the content of the scoping report, requesting that the environmental impact assessment (EIA) process be paused until detailed objections are submitted.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement