APPEAL TO THE APPEAL AUTHORITY, DEPARTMENT OF ECONOMIC DEVELOPMENT, ENVIRONMENT AND TOURISM, LIMPOPO
This document is a formal appeal submitted by the Centre for Environmental Rights (CER) on behalf of four appellants—Earthlife Africa, groundWork, the Mining and Environmental Justice Community Network of South Africa, and Dzomo La Mupo—to the Member of the Executive Council (MEC) of the Limpopo Department of Economic Development, Environment and Tourism (LEDET). The appeal seeks to set aside Environmental Authorisation (EA) No. 12/1/9/2-V79, granted on 23 February 2022 to the Musina-Makhado Special Economic Zone (SOC) Ltd (MMSEZ). The EA allows for the site clearance of 3,863 hectares of indigenous vegetation and the development of bulk infrastructure in the Vhembe District of Limpopo. The appellants argue that the EA is unlawful due to procedural irregularities, a lack of authority by the decision-maker, failure to assess cumulative and climate impacts, and the disregard of cultural heritage and water scarcity issues.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
ENVIRONMENTAL AUTHORISATION FOR THE CONSTRUCTION OF A 600 MW COAL-FIRED INDEPENDENT POWER PLANT AND ASSOCIATED INFRASTRUCTURE FOR KIPOWER (PTY) LIMITED SOUTH AFRICA / CLIMATE CHANGE IMPACT ASSESSMENT
A letter from MacRobert Attorneys to the Centre for Environmental Rights (CER) regarding the environmental authorisation for a 600 MW coal-fired independent power plant for KiPower (Pty) Limited in South Africa. The letter confirms the developer's intent to conduct a Climate Change Impact Assessment (CCIA) following a specific court judgement.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
ENVIRONMENTAL AUTHORISATION FOR THE CONSTRUCTION OF A 600 MW COAL-FIRED INDEPENDENT POWER PLANT AND ASSOCIATED INFRASTRUCTURE FOR KIPOWER (PTY) LIMITED SOUTH AFRICA
A letter from MacRobert Attorneys, acting for KiPower (Pty) Ltd and Kuyasa Mining (Pty) Ltd, responding to the Centre for Environmental Rights regarding the environmental authorisation for a proposed 600 MW coal-fired independent power plant in South Africa.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
ENVIRONMENTAL AUTHORISATION ISSUED IN RESPECT OF THE PROPOSED CONSTRUCTION OF A 600MW COAL-FIRED INDEPENDENT POWER PLANT (IPP) AND ASSOCIATED INFRASTRUCTURE FOR KIPOWER (PTY) LIMITED SOUTH AFRICA NEAR DELMAS, IN MPUMALANGA
The Centre for Environmental Rights (CER) is challenging the South African Minister of Environmental Affairs' decision to authorize a 600MW coal-fired power plant for KiPower (Pty) Limited near Delmas, Mpumalanga. Citing the 'Thabametsi judgment', the CER argues that the law requires a comprehensive climate change impact assessment—covering GHG emissions, water scarcity, and social costs—before such authorization is granted. The CER has proposed a legal settlement to require this assessment and set aside the previous decision.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
RECOMMENDATIONS REGARDING THE NATIONAL ENVIRONMENTAL MANAGEMENT ACT: NATIONAL APPEAL REGULATIONS, 2014
The Centre for Environmental Rights (CER) submitted recommendations to the Department of Environmental Affairs to amend the National Environmental Management Act (NEMA): National Appeal Regulations, 2014. The CER argues that the current regulations may violate the right to just administrative action under the Constitution and the Promotion of Administrative Justice Act, 2000 (PAJA), specifically regarding restrictive timeframes and procedural fairness for interested and affected parties (I&APs).
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
APPELLANT’S ANSWERING STATEMENT IN TERMS OF REGULATION 63(2) (b) OF THE ENVIRONMENTAL IMPACT ASSESSMENT REGULATIONS, 2010 GN R543 IN GG 33306
This Answering Statement, filed by groundWork through the Centre for Environmental Rights, challenges the environmental authorisation granted to Kuyasa Mining (Pty) Ltd for a 600 MW coal-fired power plant near Delmas, Mpumalanga. The Appellant argues that the Environmental Assessment Practitioner (EAP) lacked independence, the project's location in a Highveld Priority Area hotspot will exacerbate air pollution, and the environmental impact assessment failed to adequately address climate change and water scarcity.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement
KM_C554e-20151021093225
The Department of Environmental Affairs of South Africa has granted an integrated environmental authorisation to Kuyasa Mining (Pty) Ltd on behalf of KiPower (Pty) Ltd for the construction of a 600MW coal-fired independent power plant and associated infrastructure near Delmas in the Mpumalanga Province.
AI-generated
This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.
Document type: Statement