Working Together Assessing Public–Private Partnerships in Africa
Summary
The report examines the record of public-private partnerships (PPPs) in Africa, arguing that while they can address infrastructure backlogs, they are not a 'magic bullet' and are prone to the same failures as privatisation, including corruption and high consumer costs. Through eight case studies in transport, prisons, telecommunications, water, power, and eco-tourism, the document highlights that success depends on thorough feasibility studies, strong political commitment, and effective regulatory frameworks. Key failures are attributed to a lack of transparency, poor risk management, and unrealistic design specifications. The report recommends that African governments build institutional capacity, implement integrity pacts to combat graft, and adopt a phased approach by starting with smaller projects.
Key insights
- PPPs in Africa have a mixed record over the last 15 years and should not be viewed as a universal solution for infrastructure and service gaps.
- The N4 toll road between South Africa and Mozambique demonstrated that PPPs are viable in the road sector when users are able to pay, utilizing cross-subsidisation to manage risks in poorer areas.
- The Maputo Port concession increased efficiency and handling volumes from 4.3 million tonnes in 2002 to 5.54 million tonnes in 2004.
- South African prison PPPs provided higher quality facilities than public prisons, but costs were inflated by overly high design specifications and a lack of initial affordability studies.
- Uganda successfully expanded telecommunications access by using competition and a regulatory framework that included financial incentives and subsidies for rural coverage.
- Water concessions at the municipal level, such as the Dolphin Coast project in South Africa, often struggle with commercial viability, high non-payment rates, and the inability of small municipalities to negotiate effectively with multinationals.
- Multi-utility provision in Gabon was relatively successful due to strong political commitment and the ability to cross-subsidise the water sector using electricity revenues.
- The power purchasing agreement with Independent Power Tanzania Limited (IPTL) is cited as a failure due to corruption, lack of feasibility studies, and the purchase of unnecessary capacity at inflated prices.
- Eco-tourism PPPs, such as the Nature's Group concession in Kruger National Park, can increase profits and service quality but may face staff resistance and risks from inexperienced private partners.
- Corruption remains a critical barrier to successful PPPs in Africa, often manifesting as bribes for concessions or the awarding of contracts to political cronies.
Cite the original document
- APA
- Farlam, P. (2005). Working Together Assessing Public–Private Partnerships in Africa. South African Institute of International Affairs. https://saiia.org.za/wp-content/uploads/2008/03/Nepad-Policy-Focus-Assessing-Public-Private-Partnerships-Africa-1.pdf
- Chicago
- Farlam, Peter. Working Together Assessing Public–Private Partnerships in Africa. South African Institute of International Affairs, 2005. https://saiia.org.za/wp-content/uploads/2008/03/Nepad-Policy-Focus-Assessing-Public-Private-Partnerships-Africa-1.pdf.
- Wikipedia
- {{cite report |last1=Farlam |first1=Peter |title=Working Together Assessing Public–Private Partnerships in Africa |publisher=South African Institute of International Affairs |date=February 2005 |url=https://saiia.org.za/wp-content/uploads/2008/03/Nepad-Policy-Focus-Assessing-Public-Private-Partnerships-Africa-1.pdf |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @techreport{farlam2005working, author = {Farlam, Peter}, title = {{Working Together Assessing Public–Private Partnerships in Africa}}, institution = {South African Institute of International Affairs}, year = {2005}, month = feb, url = {https://saiia.org.za/wp-content/uploads/2008/03/Nepad-Policy-Focus-Assessing-Public-Private-Partnerships-Africa-1.pdf}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated