Independent Monitoring of the Ogoniland Clean-up
Summary
The report finds that the Ogoniland clean-up is considerably delayed, with 15 out of 21 sampled lots failing to meet statutory hydrocarbon pollution thresholds for close-out.
Key insights
- The completion of the first phase of the clean-up at 'simple' sites is significantly delayed; while contractors report completion at 47 out of 50 sites, only 26 have been government-certified as complete.
- Independent sampling of 21 lots revealed that 15 lots had at least one sample exceeding the Total Petroleum Hydrocarbon (TPH) thresholds established by NOSDRA, with 19% of all samples collected exceeding these limits.
- Significant contamination persists at specific sites, notably Lot 22, which had 29 samples exceeding thresholds with a maximum TPH level of 13,812 mg/kg, and Lots 16, 49, and 51, which showed high groundwater pollution.
- There is a concerning discrepancy between local and international laboratory results; an ILAC-accredited laboratory in the UK reported TPH levels an average of 83% higher than the local Nigerian laboratory.
- Poor remediation practices are causing environmental damage, including the mixing of topsoil and subsoil during backfilling, which has resulted in a lack of vegetative growth and damaged agricultural viability at several sites.
- Community awareness of the clean-up has improved, with 89% of 1,500 survey respondents showing good basic awareness in December 2022, and the awareness gap between men and women has narrowed.
- The delivery of emergency measures is extremely slow; only one of six planned water schemes (Alesa) is operational, and there are no established health registries despite UNEP recommendations.
- Livelihood programmes are facing delays and transparency issues, specifically regarding the selection process for a technical vocational skills acquisition programme and the lack of a target for female participation.
- The establishment of the Centre of Excellence for Environmental Restoration (CEER) and the Integrated Contaminated Soil Management Centre (ICSMC) has been slow, though land surveys and architectural design approvals have been completed.
- The Central Representative and Advisory Committee (CRAC) is perceived as 'faceless' and non-responsive, with 53% of surveyed communities reporting that none of their complaints were effectively addressed by the committee.
Cite the original document
- APA
- Stakeholder Democracy Network (2023). Independent Monitoring of the Ogoniland Clean-up. https://sdn.ngo/wp-content/uploads/2023/10/Fourth-Biannual-Report-of-CSO-Monitoring-of-Clean-up.pdf
- Chicago
- Stakeholder Democracy Network. Independent Monitoring of the Ogoniland Clean-up. 2023. https://sdn.ngo/wp-content/uploads/2023/10/Fourth-Biannual-Report-of-CSO-Monitoring-of-Clean-up.pdf.
- Wikipedia
- {{cite report |author=Stakeholder Democracy Network |title=Independent Monitoring of the Ogoniland Clean-up |date=2023 |url=https://sdn.ngo/wp-content/uploads/2023/10/Fourth-Biannual-Report-of-CSO-Monitoring-of-Clean-up.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document sdn-000105)}}
- BibTeX
- @techreport{stakeholderdemocracynetwork2023independent, author = {{Stakeholder Democracy Network}}, title = {{Independent Monitoring of the Ogoniland Clean-up}}, institution = {Stakeholder Democracy Network}, year = {2023}, url = {https://sdn.ngo/wp-content/uploads/2023/10/Fourth-Biannual-Report-of-CSO-Monitoring-of-Clean-up.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document sdn-000105} }
Full text
Collected · Record updated