Komati’s Just Transition
Summary
The report finds that while stakeholder engagement and community inclusivity have improved significantly, progress on decommissioning and repowering activities has been limited by procurement delays and bureaucratic challenges.
Key insights
- Progress on decommissioning (Component A) and repowering (Component B) under the World Bank-funded Eskom Just Energy Transition Project (EJETP) has been limited since late 2023, primarily due to procurement challenges and uncertainty regarding infrastructure demolition.
- Environmental assessments determined that the originally planned 70 MW of wind capacity at Komati Power Station is not feasible due to potential negative impacts on the local ecosystem and grid infrastructure, leading Eskom to increase the solar PV capacity in Phase 1 to 72 MW.
- Stakeholder engagement has improved significantly, with the establishment of the Ward 4 Komati Community Steering Committee (Steer Co) and the Komati Stakeholder Forum, allowing the community to take a more active role in decision-making.
- Reskilling and upskilling efforts from October 2022 through 2024 provided training to 393 Eskom workers and community members in areas such as renewable energy and soft skills, though many trainees are still awaiting the start of projects to apply these skills.
- Short-term employment has been created through projects such as an invasive alien species removal project employing 186 community members in 2024 and the Social Employment Fund (SEF), which launched in January 2025 to provide part-time work for 300 community members.
- Economic diversification initiatives include the establishment of an agrivoltaics plant, an aquaponics system, and a containerised microgrid assembly line, though the latter is currently paused to improve production costs and commercial viability.
- Community development remains a major challenge, with critical gaps in infrastructure such as clinics, libraries, and basic services; however, Breadline Africa is planning an early childhood development (ECD) hub in Komati with construction targeted for October 2025.
- The disbursement of World Bank funds under the EJETP has been slow, with slightly more than US$2.3 million disbursed by the end of 2024, largely due to delays in Components A and B.
- Six key lessons for just transitions emerged: starting early to enable proper sequencing, avoiding premature conclusions about failure or success, using innovative funding models, maintaining a long-term vision, focusing on results-oriented engagement, and clearly designating responsibility to overcome coordination challenges.
Cite the original document
- APA
- JUST SA (2025). Komati’s Just Transition. https://www.justsaportal.org.za/uploads/files/PCC-Komati-Progress-Report_FINAL-5.27.pdf
- Chicago
- JUST SA. Komati’s Just Transition. 2025. https://www.justsaportal.org.za/uploads/files/PCC-Komati-Progress-Report_FINAL-5.27.pdf.
- Wikipedia
- {{cite report |author=JUST SA |title=Komati’s Just Transition |date=June 2025 |url=https://www.justsaportal.org.za/uploads/files/PCC-Komati-Progress-Report_FINAL-5.27.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document justsa-000019)}}
- BibTeX
- @techreport{justsa2025komatis, author = {{JUST SA}}, title = {{Komati’s Just Transition}}, institution = {JUST SA}, year = {2025}, month = jun, url = {https://www.justsaportal.org.za/uploads/files/PCC-Komati-Progress-Report_FINAL-5.27.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document justsa-000019} }
Full text
Collected · Record updated