Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power
Summary
The report finds that Pakistan's IGCEP 2047 plan risks locking in unsustainable overcapacity and expensive power by overestimating demand and neglecting the cost-effectiveness of renewable energy.
Key insights
- The IGCEP's Medium demand growth forecast, which serves as the foundation for the Base Case scenario, is over-optimistic because it assumes GDP growth will increase to 5.5% by 2025 and remain there until 2047, ignoring the 2019 GDP growth of 3.3% and the economic impact of the COVID-19 pandemic.
- Under the IGCEP Base Case scenario, imported coal-fired power plants expected to be operational by 2030 will have a collective utilisation rate of only 14%, rendering them stranded assets that cannot operate commercially without generous capacity payments.
- The IGCEP neglects renewable energy after 2030, modelling no further wind power additions and showing the overall contribution of renewables to power capacity dropping from 31% in 2030 to 23% in 2047.
- The plan models the addition of 20,000MW of LNG-fired power capacity between 2030 and 2047, yet predicts that generation from this source will collapse, resulting in a utilisation rate of just 0.8% by 2047.
- The IGCEP's focus on domestic coal-fired power is predicted to cause annual carbon emissions to almost triple by 2047 compared to 2020 levels, creating significant carbon risk, including potential EU carbon border taxes.
- The IGCEP models the addition of over 35,000MW of hydro power between 2030 and 2047, including the Diamer-Bhasha Dam project expected to cost approximately US$14 billion, though the report argues these are hard to justify given cheaper, quicker alternatives.
Cite the original document
- APA
- Nicholas, S. (2020). Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf
- Chicago
- Nicholas, Simon. Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power. Institute for Energy Economics and Financial Analysis, 2020. https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf.
- Wikipedia
- {{cite report |last1=Nicholas |first1=Simon |title=Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power |publisher=Institute for Energy Economics and Financial Analysis |date=September 2020 |url=https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001780)}}
- BibTeX
- @techreport{nicholas2020pakistan, author = {Nicholas, Simon}, title = {{Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2020}, month = sep, url = {https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001780} }
Full text
Collected · Record updated