Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The report finds that Pakistan's IGCEP 2047 plan risks locking in unsustainable overcapacity and expensive power by overestimating demand and neglecting the cost-effectiveness of renewable energy.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The IGCEP's Medium demand growth forecast, which serves as the foundation for the Base Case scenario, is over-optimistic because it assumes GDP growth will increase to 5.5% by 2025 and remain there until 2047, ignoring the 2019 GDP growth of 3.3% and the economic impact of the COVID-19 pandemic.
  • Under the IGCEP Base Case scenario, imported coal-fired power plants expected to be operational by 2030 will have a collective utilisation rate of only 14%, rendering them stranded assets that cannot operate commercially without generous capacity payments.
  • The IGCEP neglects renewable energy after 2030, modelling no further wind power additions and showing the overall contribution of renewables to power capacity dropping from 31% in 2030 to 23% in 2047.
  • The plan models the addition of 20,000MW of LNG-fired power capacity between 2030 and 2047, yet predicts that generation from this source will collapse, resulting in a utilisation rate of just 0.8% by 2047.
  • The IGCEP's focus on domestic coal-fired power is predicted to cause annual carbon emissions to almost triple by 2047 compared to 2020 levels, creating significant carbon risk, including potential EU carbon border taxes.
  • The IGCEP models the addition of over 35,000MW of hydro power between 2030 and 2047, including the Diamer-Bhasha Dam project expected to cost approximately US$14 billion, though the report argues these are hard to justify given cheaper, quicker alternatives.

Cite the original document

APA
Nicholas, S. (2020). Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf
Chicago
Nicholas, Simon. Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power. Institute for Energy Economics and Financial Analysis, 2020. https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf.
Wikipedia
{{cite report |last1=Nicholas |first1=Simon |title=Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power |publisher=Institute for Energy Economics and Financial Analysis |date=September 2020 |url=https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001780)}}
BibTeX
@techreport{nicholas2020pakistan, author = {Nicholas, Simon}, title = {{Pakistan Risks Locking in Long-Term Overcapacity and Expensive Power}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2020}, month = sep, url = {https://ieefa.org/sites/default/files/2022-05/Pakistan-Risks-Locking-in-Long-Term-Overcapacity_Expensive-Power_September-2020_0.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001780} }

Full text

Collected · Record updated