Pakistan’s vast hydropower pipeline at risk of not being materialized
Summary
This IEEFA fact sheet finds that Pakistan's 14 GW hydropower pipeline is at high risk of failure, with only 15% of planned capacity estimated to come online on time due to financial instability and climate vulnerability.
Key insights
- Pakistan aims to bring almost 14 GW of hydropower capacity online by 2030, which, combined with existing capacity, would make hydropower responsible for 46% of the country's total power generation.
- The hydropower pipeline faces severe implementation delays and financial hurdles: as of September 2022, only 51% of the capacity had achieved financial closure and only 39% had begun physical construction.
- IEEFA estimates that only 15% of the planned capacity will come online on time, and the total cost of the pipeline could increase from the current USD 31.2 billion to between USD 49 billion and USD 61 billion.
- Economic instability, including a 30% loss in the value of the Pakistani rupee in 2022 and inflation at a 47-year high of 27.26%, combined with credit rating downgrades for the government and WAPDA, hinders the ability to raise capital.
- The pipeline is increasingly vulnerable to climate change and extreme weather; record-breaking heatwaves and lack of rainfall have already reduced water levels in major reservoirs including Tarbela, Mangla, and Chashma.
Cite the original document
- APA
- Isaad, H. (n.d.). Pakistan’s vast hydropower pipeline at risk of not being materialized. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2022-09/IEEFA%20Fact%20Sheet%20-%20Pakistan%E2%80%99s%20Vast%20Hydropower%20Pipeline%20at%20Risk%20of%20Not%20Being%20Materialized.pdf
- Chicago
- Isaad, Haneea. Pakistan’s vast hydropower pipeline at risk of not being materialized. Institute for Energy Economics and Financial Analysis, n.d. https://ieefa.org/sites/default/files/2022-09/IEEFA%20Fact%20Sheet%20-%20Pakistan%E2%80%99s%20Vast%20Hydropower%20Pipeline%20at%20Risk%20of%20Not%20Being%20Materialized.pdf.
- Wikipedia
- {{cite report |last1=Isaad |first1=Haneea |title=Pakistan’s vast hydropower pipeline at risk of not being materialized |publisher=Institute for Energy Economics and Financial Analysis |url=https://ieefa.org/sites/default/files/2022-09/IEEFA%20Fact%20Sheet%20-%20Pakistan%E2%80%99s%20Vast%20Hydropower%20Pipeline%20at%20Risk%20of%20Not%20Being%20Materialized.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001364)}}
- BibTeX
- @techreport{isaadndpakistans, author = {Isaad, Haneea}, title = {{Pakistan’s vast hydropower pipeline at risk of not being materialized}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2022-09/IEEFA%20Fact%20Sheet%20-%20Pakistan%E2%80%99s%20Vast%20Hydropower%20Pipeline%20at%20Risk%20of%20Not%20Being%20Materialized.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001364} }
Full text
Collected · Record updated