How Europe’s grid operators are preparing for the energy transition
Summary
This report finds that most European grid operators are failing to align their long-term plans with a fossil-free power system by 2035, resulting in massive connection queues and high curtailment costs. It highlights the UK's creation of the National Energy System Operator (NESO) as a model for independent system planning.
Key insights
- Significant queues of renewable energy and hybrid projects are waiting for grid connections across Europe, with a conservative estimate of 1,700 GW waiting across 16 countries as of 2024-2025. The volume of projects in these queues exceeds the additional installation required to reach 2030 national energy and climate plan targets.
- The majority of TSOs rely on outdated national energy plans that assume significant fossil gas capacity by 2035, with only five TSOs considering scenarios aligned with a decarbonised power system by 2035: Energinet, Fingrid, Eirgrid, NESO, and Litgrid.
- Grid connection processes are often inefficient, with 19 of 25 TSOs still using a 'first come, first served' approach, which can lead to the inclusion of 'zombie' projects—speculative applications unlikely to be built.
- Governance and independence vary across Europe, with 10 TSOs failing to meet the most robust form of legal ownership unbundling, meaning they remain part of portfolios involved in generating or selling electricity.
- There is a lack of climate integration in the mandates of energy regulators and TSOs; 19 of 30 regulators make no public reference to climate neutrality in their responsibilities, and only 13 TSOs have climate commitments or targets.
- The UK has established a leadership position by creating the National Energy System Operator (NESO), a fully independent public body responsible for both electricity and gas system planning and operation with a legal duty to support net zero.
- Financial capacity for grid upgrades varies, with 14 of 23 analysed TSOs holding investment-grade ratings, and 11 having issued green bonds to fund sustainable infrastructure.
- Dynamic line rating (DLR) technology, which can boost capacity by up to 40%, is underutilised; only three TSOs (Elia, Energinet, and ELES) have fully implemented it across all overhead lines.
Cite the original document
- APA
- Institute for Energy Economics and Financial Analysis (2025). How Europe’s grid operators are preparing for the energy transition. https://ieefa.org/sites/default/files/2025-09/How%20Europe%E2%80%99s%20grid%20operators%20are%20preparing%20for%20the%20energy%20transition_May%202025_0.pdf
- Chicago
- Institute for Energy Economics and Financial Analysis. How Europe’s grid operators are preparing for the energy transition. 2025. https://ieefa.org/sites/default/files/2025-09/How%20Europe%E2%80%99s%20grid%20operators%20are%20preparing%20for%20the%20energy%20transition_May%202025_0.pdf.
- Wikipedia
- {{cite report |author=Institute for Energy Economics and Financial Analysis |title=How Europe’s grid operators are preparing for the energy transition |date=May 2025 |url=https://ieefa.org/sites/default/files/2025-09/How%20Europe%E2%80%99s%20grid%20operators%20are%20preparing%20for%20the%20energy%20transition_May%202025_0.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001306)}}
- BibTeX
- @techreport{instituteforenergyeconomicsandfinancialanalysis2025how, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{How Europe’s grid operators are preparing for the energy transition}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2025}, month = may, url = {https://ieefa.org/sites/default/files/2025-09/How%20Europe%E2%80%99s%20grid%20operators%20are%20preparing%20for%20the%20energy%20transition_May%202025_0.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001306} }
Full text
Collected · Record updated