Environmental Due Diligence (EDD) Of Renewable Energy Projects
Summary
The guidelines outline a three-stage EDD process for biogas systems: establishing a regulatory framework, performing an environmental appraisal, and monitoring the project post-approval. The appraisal stage uses a risk rating key (Low to High) and checklists to evaluate issues such as methane emissions, effluent contamination, worker safety, and public perception. It also identifies environmental opportunities, such as the use of digestate as soil conditioner or fertilizer and the reduction of feedstock pollution. The process concludes with cost estimation for risk management and ongoing monitoring requirements based on the project's risk level.
Key insights
- The Environmental Due Diligence (EDD) process for biogas systems is structured into three distinct stages: establishing the regulatory framework, conducting an environmental appraisal, and monitoring the project after approval.
- The environmental appraisal stage involves four core steps: assessing environmental risks, determining mitigation measures, estimating the costs of managing those risks, and reporting the results.
- Biogas projects are evaluated against a risk rating key ranging from Low (L) to High (H), based on information availability, the severity of potential environmental impact, the probability of occurrence, and the availability of mitigation measures.
- Key environmental and social risks associated with biogas systems include methane emissions from storage and leaks, contamination of water from effluents, occupational hazards like explosions or asphyxiation, and public perception issues such as odour and visual intrusion.
- Biogas systems offer several environmental opportunities, including the creation of sustainable waste management systems, the production of solid digestate for use as a soil conditioner or peat substitute, and the use of liquid digestate as fertilizer.
- Post-approval monitoring requirements vary by risk level: high-risk projects require legal clauses for environmental reporting and evaluation, including independent site visits or audits every six to twelve months, while low and moderate risk projects may only require annual or semi-annual reports from the sponsor.
Cite the original document
- APA
- Basel Agency for Sustainable Energy (n.d.). Environmental Due Diligence (EDD) Of Renewable Energy Projects. https://energy-base.org/wp-content/uploads/2020/03/6.EDD-Biogas-Systems.pdf
- Chicago
- Basel Agency for Sustainable Energy. Environmental Due Diligence (EDD) Of Renewable Energy Projects. n.d. https://energy-base.org/wp-content/uploads/2020/03/6.EDD-Biogas-Systems.pdf.
- Wikipedia
- {{cite report |author=Basel Agency for Sustainable Energy |title=Environmental Due Diligence (EDD) Of Renewable Energy Projects |url=https://energy-base.org/wp-content/uploads/2020/03/6.EDD-Biogas-Systems.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document enbase-000031)}}
- BibTeX
- @techreport{baselagencyforsustainableenergyndenvironmental, author = {{Basel Agency for Sustainable Energy}}, title = {{Environmental Due Diligence (EDD) Of Renewable Energy Projects}}, institution = {Basel Agency for Sustainable Energy}, url = {https://energy-base.org/wp-content/uploads/2020/03/6.EDD-Biogas-Systems.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document enbase-000031} }
Full text
Collected · Record updated