APPROACHING THE MILESTONE: THE IMPENDING END OF NEW COAL POWER PLANT CONSTRUCTION
Summary
The document finds that while most of the world is rapidly retreating from new coal power, China's increasing pre-construction pipeline offsets global progress, leaving China home to 66% of proposed capacity as of July 2022.
Key insights
- Between 2015 and 2022, 76% of planned coal power worldwide was scrapped, a figure that has remained stable into 2022 because China's new proposals offset progress in other countries.
- As of July 2022, there was 298 GW of pre-construction capacity under development across 34 countries, with China accounting for 66% (197 GW) of this total.
- The EU27 is the first world region to reach the milestone of having no new coal projects under consideration, following the decision to shelve the Leczna Power Plant in Poland.
- China's commitment to end support for overseas coal power plants has led to the cancellation of 21 GW of capacity across 26 plants in 15 countries.
- South-East Asia has seen an 81% contraction of its new coal project pipeline since 2015, driven by reductions in national energy plans in Indonesia and Viet Nam.
Cite the original document
- APA
- SENLEN, O., BLITZER, H., ROBERTS, L., & LITTLECOTT, C. (2022). APPROACHING THE MILESTONE: THE IMPENDING END OF NEW COAL POWER PLANT CONSTRUCTION. E3G. https://www.e3g.org/wp-content/uploads/E3G-No-New-Coal-Briefing-Paper-COP27-IEA.pdf
- Chicago
- SENLEN, OYKU, HANNAH BLITZER, LEO ROBERTS, and CHRIS LITTLECOTT. APPROACHING THE MILESTONE: THE IMPENDING END OF NEW COAL POWER PLANT CONSTRUCTION. E3G, 2022. https://www.e3g.org/wp-content/uploads/E3G-No-New-Coal-Briefing-Paper-COP27-IEA.pdf.
- Wikipedia
- {{cite report |last1=SENLEN |first1=OYKU |last2=BLITZER |first2=HANNAH |last3=ROBERTS |first3=LEO |last4=LITTLECOTT |first4=CHRIS |title=APPROACHING THE MILESTONE: THE IMPENDING END OF NEW COAL POWER PLANT CONSTRUCTION |publisher=E3G |date=November 2022 |url=https://www.e3g.org/wp-content/uploads/E3G-No-New-Coal-Briefing-Paper-COP27-IEA.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document e3g-000956)}}
- BibTeX
- @techreport{senlen2022approaching, author = {SENLEN, OYKU and BLITZER, HANNAH and ROBERTS, LEO and LITTLECOTT, CHRIS}, title = {{APPROACHING THE MILESTONE: THE IMPENDING END OF NEW COAL POWER PLANT CONSTRUCTION}}, institution = {E3G}, year = {2022}, month = nov, url = {https://www.e3g.org/wp-content/uploads/E3G-No-New-Coal-Briefing-Paper-COP27-IEA.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document e3g-000956} }