Senegal’s Gas-to-Power Ambitions
Summary
Senegal's plan to develop over 3 GW of gas-to-power capacity by 2050 faces significant risks of gas supply shortages and a funding gap of at least USD 2.2 billion. The report argues that a more balanced energy mix with a stronger emphasis on renewables offers a more secure and cost-effective pathway.
Key insights
- Senegal's recent plans to develop more than 3 gigawatts (GW) of gas-to-power capacity by 2050 may be hindered by an inability to extract sufficient gas and a struggle to raise at least USD 2.2 billion for necessary infrastructure.
- If only the plans detailed in the IEA policy review are realized, gas will dominate the long-term power mix, comprising 75 percent of installed capacity by 2050, potentially locking the country into gas use and inhibiting the catalytic effect of the Just Energy Transition Partnership (JETP).
- The Yakaar-Teranga project is critical for domestic gas supply, but its development is highly uncertain due to BP's withdrawal, potential contract renegotiations by the new administration, and the global energy transition.
- The pool of financing for gas-to-power is shrinking globally due to climate concerns, with Africa's share of global gas power generation investment falling from 12 percent in 2015 to 5 percent in 2023.
- To reach the JETP target of 40 percent renewables by 2030, Senegal needs an additional 346 MW of renewables capacity, which is estimated to cost approximately $920 million, excluding grid upgrades and storage.
- The use of Combined Cycle Gas Turbine (CCGT) plants for baseload generation creates a high risk of carbon lock-in; the report suggests Open Cycle Gas Turbines (OCGTs) or reciprocating engine turbines are better suited as 'peakers' to complement renewables.
- Senegal's energy planning lacks transparency, with key documents like the Gas Masterplan and Power Generation Masterplan not in the public domain, and the JETP was nearly signed without consulting parliamentarians or civil society.
- The government faces a dilemma regarding Yakaar-Teranga: negotiating high domestic volumes to avoid shortages risks costly take-or-pay penalties if other projects (GTA and Sangomar) also deliver domestic gas.
Cite the original document
- APA
- DIENE, P. D., SCURFIELD, T., SAYNE, A., & OBEID, J. (2024). Senegal’s Gas-to-Power Ambitions. Natural Resource Governance Institute. https://resourcegovernance.org/sites/default/files/2024-07/Senegal-Gas-to-Power-Ambitions_Securing-Scale-Sustainability.pdf
- Chicago
- DIENE, PAPA DAOUDA, THOMAS SCURFIELD, AARON SAYNE, and JESSICA OBEID. Senegal’s Gas-to-Power Ambitions. Natural Resource Governance Institute, 2024. https://resourcegovernance.org/sites/default/files/2024-07/Senegal-Gas-to-Power-Ambitions_Securing-Scale-Sustainability.pdf.
- Wikipedia
- {{cite report |last1=DIENE |first1=PAPA DAOUDA |last2=SCURFIELD |first2=THOMAS |last3=SAYNE |first3=AARON |last4=OBEID |first4=JESSICA |title=Senegal’s Gas-to-Power Ambitions |publisher=Natural Resource Governance Institute |date=June 2024 |url=https://resourcegovernance.org/sites/default/files/2024-07/Senegal-Gas-to-Power-Ambitions_Securing-Scale-Sustainability.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document NRGI-000797)}}
- BibTeX
- @techreport{diene2024senegals, author = {DIENE, PAPA DAOUDA and SCURFIELD, THOMAS and SAYNE, AARON and OBEID, JESSICA}, title = {{Senegal’s Gas-to-Power Ambitions}}, institution = {Natural Resource Governance Institute}, year = {2024}, month = jun, url = {https://resourcegovernance.org/sites/default/files/2024-07/Senegal-Gas-to-Power-Ambitions_Securing-Scale-Sustainability.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document NRGI-000797} }
Full text
Collected · Record updated