REHABILITATION OF THE RAILWAYS IN THE SOUTH CAUCASUS: ASSESSMENT OF THE POTENTIAL ECONOMIC BENEFITS Sochi-Sukhum/i-Tbilisi-Yerevan railway
Summary
The report concludes that restoring the Sochi-Sukhum/i-Tbilisi-Yerevan railway is economically irrational due to high restoration costs and insufficient potential freight volumes, making the project unattractive for investment.
Key insights
- The total estimated cost to restore the Sochi-Sukhum/i-Tbilisi-Yerevan railway route is US$277.5 million, with US$251 million required for the Psou-Ingur/i segment and US$26.5 million for the Ingur/i-Ingiri (Zugdidi) section.
- Investment in the 190 km railway segment through Abkhazia is highly unprofitable; even with a maximum cargo of 10 million tons per year, it would not be profitable for at least 16 years, and based on current cargo amounts, a return on investment would only occur in 200 years.
- The profitability threshold of 10 million tons of cargo per year is considered unachievable, as the most optimistic freight scenario forecasts no more than four million tons annually.
- Restoring the railway would likely have a negative economic effect on Georgia by reducing revenue for the seaport of Poti and causing job losses in the automobile freight transport sector, where 300-400 jobs could be lost.
- For Armenia, a direct railway connection to Russia would be economically beneficial in the medium to long term, potentially reducing transport costs for importers and exporters by an average of 20%.
- The mining industry in Armenia, specifically the Tekhut deposit in the Lori district, could see significant growth if a direct railway to Russia were opened, potentially increasing annual production from 12,000 tons to between 95,000 and 100,000 tons.
- Case studies of major Georgian enterprises, including Rustavi Azot, Hipp-Georgia, and the Zestafoni Ferrous Alloy Plant, indicate that these companies are already operating at or near full capacity and would not increase production even if the Russian market became more accessible via railway.
Cite the original document
- APA
- International Alert (2013). REHABILITATION OF THE RAILWAYS IN THE SOUTH CAUCASUS: ASSESSMENT OF THE POTENTIAL ECONOMIC BENEFITS Sochi-Sukhum/i-Tbilisi-Yerevan railway. https://www.international-alert.org/app/uploads/2021/08/Caucasus-Railways-Rehabilitation-Pt1-EN-2013.pdf
- Chicago
- International Alert. REHABILITATION OF THE RAILWAYS IN THE SOUTH CAUCASUS: ASSESSMENT OF THE POTENTIAL ECONOMIC BENEFITS Sochi-Sukhum/i-Tbilisi-Yerevan railway. 2013. https://www.international-alert.org/app/uploads/2021/08/Caucasus-Railways-Rehabilitation-Pt1-EN-2013.pdf.
- Wikipedia
- {{cite report |author=International Alert |title=REHABILITATION OF THE RAILWAYS IN THE SOUTH CAUCASUS: ASSESSMENT OF THE POTENTIAL ECONOMIC BENEFITS Sochi-Sukhum/i-Tbilisi-Yerevan railway |date=2013 |url=https://www.international-alert.org/app/uploads/2021/08/Caucasus-Railways-Rehabilitation-Pt1-EN-2013.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document intalert-000102)}}
- BibTeX
- @techreport{internationalalert2013rehabilitation, author = {{International Alert}}, title = {{REHABILITATION OF THE RAILWAYS IN THE SOUTH CAUCASUS: ASSESSMENT OF THE POTENTIAL ECONOMIC BENEFITS Sochi-Sukhum/i-Tbilisi-Yerevan railway}}, institution = {International Alert}, year = {2013}, url = {https://www.international-alert.org/app/uploads/2021/08/Caucasus-Railways-Rehabilitation-Pt1-EN-2013.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document intalert-000102} }
Full text
Collected · Record updated