The report concludes that the Rampal Power Plant is a risky, over-subsidised project that would increase electricity rates in Bangladesh and poses significant financial risks to the Indian EXIM Bank.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The Rampal power plant is heavily subsidised by the Indian and Bangladeshi governments through three primary mechanisms: a 15-year income tax exemption worth US$936 million, a below-market-rate loan from the Indian EXIM Bank representing a US$988 million subsidy, and an annual US$26 million subsidy for maintenance dredging.
  • The plant's revenue requirements would necessitate tariff levels 32% higher than the current average cost of electricity production in Bangladesh; without subsidies, these costs would be 62% higher.
  • The project's location in a "Wind risk zone" and its low elevation (averaging 2 metres above sea level) make it extremely vulnerable to storm surges, outages, and damage, especially as the site elevation was lowered by NTPC from 5.5 metres to 5 metres.
  • The project poses a significant financial risk to the Indian EXIM Bank, as the US$1.6 billion loan would constitute 10.7% of the bank's total FY2015 assets and could limit its international fund-raising capacity due to violations of Equator principles.
  • The plant is designed using outdated supercritical technology rather than modern ultra-supercritical technology, which would be more efficient and produce fewer emissions.
  • The project is located near the Sundarbans, a UNESCO World Heritage site, and requires dredging a 36-kilometre stretch of the Passur River, which the Norwegian Government Pension Fund Global's Council of Ethics argues creates an unacceptable risk of severe environmental damage.
  • Bangladesh has significant potential for solar energy, with the capacity to generate 380TWh per annum; achieving a 10GW utility solar goal by 2025 would require only 0.15% of the country's land.
  • The report notes a history of delays and cost overruns for coal projects in Bangladesh, citing the Barapukuria mine's failure to meet 1998 projections and an 11-year delay for the Phulbari Coal project.

Cite the original document

APA
Institute for Energy Economics and Financial Analysis (n.d.). risky-and-over-subsidised-a-financial-analysis-of-the-rampal-power-plant-_june-2016-29dc127e2e9dffdc.pdf. https://ieefa.org/sites/default/files/resources/Risky-and-Over-Subsidised-A-Financial-Analysis-of-the-Rampal-Power-Plant-_June-2016.pdf
Chicago
Institute for Energy Economics and Financial Analysis. risky-and-over-subsidised-a-financial-analysis-of-the-rampal-power-plant-_june-2016-29dc127e2e9dffdc.pdf. n.d. https://ieefa.org/sites/default/files/resources/Risky-and-Over-Subsidised-A-Financial-Analysis-of-the-Rampal-Power-Plant-_June-2016.pdf.
Wikipedia
{{cite report |author=Institute for Energy Economics and Financial Analysis |title=risky-and-over-subsidised-a-financial-analysis-of-the-rampal-power-plant-_june-2016-29dc127e2e9dffdc.pdf |url=https://ieefa.org/sites/default/files/resources/Risky-and-Over-Subsidised-A-Financial-Analysis-of-the-Rampal-Power-Plant-_June-2016.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001911)}}
BibTeX
@techreport{instituteforenergyeconomicsandfinancialanalysisndriskyandoversubsidisedafinancialanalysisoftherampalpowerplantjune201629dc127e2e9dffdcpdf, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{risky-and-over-subsidised-a-financial-analysis-of-the-rampal-power-plant-\_june-2016-29dc127e2e9dffdc.pdf}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/resources/Risky-and-Over-Subsidised-A-Financial-Analysis-of-the-Rampal-Power-Plant-_June-2016.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001911} }

Full text

Collected · Record updated