projekti-i-propozuar-i-termocentralit-kosova-e-re-6aba34f59a6028b7.pdf

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The report concludes that the proposed Kosova e Re coal power plant would increase electricity prices for Kosovar families by 33.8% to 50%, making it a costly and outdated energy solution. It recommends that the World Bank and the US government shift their support toward renewable energy and energy efficiency instead.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The production cost of electricity from the Kosova e Re power plant is estimated to be four times higher than the current production cost in Kosovo.
  • The operation of the plant is expected to increase overall electricity prices in Kosovo by at least 33.8% and up to 50%.
  • The project would disproportionately impact low-income households; those living below the poverty line could see electricity costs consume 39.7% of their annual income.
  • The total cost of the power plant, including construction, financing, and subsidies, is estimated to reach at least 4.169 billion euros, significantly higher than the government's 1 billion euro estimate.
  • The proposed financing model requires the Kosovo Government to borrow 945 million euros to cover 70% of the project cost, which could place excessive pressure on the national banking system and deter other economic investments.
  • The project relies on optimistic economic growth assumptions; if growth is lower than expected, electricity will become even more expensive due to high fixed costs being spread over fewer megawatt-hours.
  • The World Bank and US government's support for the project is viewed as a departure from their own climate and poverty reduction policies.
  • Renewable energy and energy efficiency measures are identified as a less costly alternative that would stimulate economic development and create jobs.
  • The project lacks transparency, with essential documents such as the business plan and the Memorandum of Understanding not being made public.
  • The project's reliance on a single bidder, ContourGlobal, and the proposed high return on equity (21.5%) increase the financial risk and cost for the public.

Cite the original document

APA
Institute for Energy Economics and Financial Analysis (n.d.). projekti-i-propozuar-i-termocentralit-kosova-e-re-6aba34f59a6028b7.pdf. https://ieefa.org/wp-content/uploads/2016/01/Projekti-i-propozuar-i-Termocentralit-Kosova-e-Re.pdf
Chicago
Institute for Energy Economics and Financial Analysis. projekti-i-propozuar-i-termocentralit-kosova-e-re-6aba34f59a6028b7.pdf. n.d. https://ieefa.org/wp-content/uploads/2016/01/Projekti-i-propozuar-i-Termocentralit-Kosova-e-Re.pdf.
Wikipedia
{{cite report |author=Institute for Energy Economics and Financial Analysis |title=projekti-i-propozuar-i-termocentralit-kosova-e-re-6aba34f59a6028b7.pdf |url=https://ieefa.org/wp-content/uploads/2016/01/Projekti-i-propozuar-i-Termocentralit-Kosova-e-Re.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001843)}}
BibTeX
@techreport{instituteforenergyeconomicsandfinancialanalysisndprojektiipropozuaritermocentralitkosovaere6aba34f59a6028b7pdf, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{projekti-i-propozuar-i-termocentralit-kosova-e-re-6aba34f59a6028b7.pdf}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/wp-content/uploads/2016/01/Projekti-i-propozuar-i-Termocentralit-Kosova-e-Re.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001843} }

Full text

Collected · Record updated