46 Gigawatts of Proposed Coal-Fired Power Projects Cancelled in 12 Months, With 600 Gigawatts Cancelled Last Decade
Summary
India's coal-fired power project pipeline has shrunk significantly, with 46 GW of projects cancelled in a single year and 600 GW cancelled over the last decade, driven by the increasing economic competitiveness of renewables.
Key insights
- Between January 2019 and January 2020, India's pre-construction pipeline of coal-fired power projects was halved from 58 GW to 29 GW, with 46 GW of projects facing formal or informal cancellations during that 12-month period.
- Over the last decade, a total of 600 GW of Indian coal-fired power project proposals have been cancelled.
- The thermal power generation sector in India faces US$60 billion in financial stress, while the coal-fired project pipeline carries a stranded asset risk value of US$40 billion.
- IEEFA projects that net new additions in the coal-fired sector will be only 30 GW by FY2029/30, which is approximately half of the 61 GW projected in the Central Electricity Authority's optimal generation draft report.
- Major thermal power operators NTPC and Tata Power have decided to stop developing new coal-fired power projects, with NTPC limiting its activity to the completion of 10.8 GW of plants already under construction.
Cite the original document
- APA
- Shah, K. (2020). 46 Gigawatts of Proposed Coal-Fired Power Projects Cancelled in 12 Months, With 600 Gigawatts Cancelled Last Decade. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/India-46-gigawatts-of-coal-fired-power-projects-cancelled-in-12-months_Mar-2020.pdf
- Chicago
- Shah, Kashish. 46 Gigawatts of Proposed Coal-Fired Power Projects Cancelled in 12 Months, With 600 Gigawatts Cancelled Last Decade. Institute for Energy Economics and Financial Analysis, 2020. https://ieefa.org/sites/default/files/resources/India-46-gigawatts-of-coal-fired-power-projects-cancelled-in-12-months_Mar-2020.pdf.
- Wikipedia
- {{cite report |last1=Shah |first1=Kashish |title=46 Gigawatts of Proposed Coal-Fired Power Projects Cancelled in 12 Months, With 600 Gigawatts Cancelled Last Decade |publisher=Institute for Energy Economics and Financial Analysis |date=March 2020 |url=https://ieefa.org/sites/default/files/resources/India-46-gigawatts-of-coal-fired-power-projects-cancelled-in-12-months_Mar-2020.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001612)}}
- BibTeX
- @techreport{shah2020gigawatts, author = {Shah, Kashish}, title = {{46 Gigawatts of Proposed Coal-Fired Power Projects Cancelled in 12 Months, With 600 Gigawatts Cancelled Last Decade}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2020}, month = mar, url = {https://ieefa.org/sites/default/files/resources/India-46-gigawatts-of-coal-fired-power-projects-cancelled-in-12-months_Mar-2020.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001612} }
Full text
Collected · Record updated