This report finds that only 15% of Pakistan's planned hydropower pipeline is estimated to come online by 2030 due to systemic cost overruns, financing hurdles, and climate vulnerabilities.
Key insights
- Pakistan's Indicative Generation Capacity Expansion Plan (IGCEP 2021) projects nearly 14 GW of hydropower capacity by 2030, but IEEFA analysis indicates only 51% has achieved financial closure and 39% has begun construction.
- Only 15% of the planned hydropower pipeline is estimated to be completed on time by 2030, with 78% of projects already exceeding their initial implementation deadlines.
- Large dams in Pakistan are prone to significant cost and schedule overruns; IEEFA estimates the current pipeline cost could rise from USD 31 billion to between USD 49 billion and USD 61 billion based on global study factors.
- The Neelum Jhelum hydropower project serves as a case study for extreme failure, completing 21 years late with costs 600% higher than initial estimates, reaching a final cost of Rs. 507 billion ($4.1 billion).
- The Diamer Bhasha dam is currently valued at USD 14 billion, but its 2029 completion date is considered highly unlikely as physical progress on the dam is only 7% and funding is currently limited to the dam site.
- Credit downgrades by Moody’s, Fitch, and S&P for both the Government of Pakistan and the Water and Power Development Authority (WAPDA) hinder the ability to raise capital and increase the cost of debt financing.
- Hydropower is increasingly vulnerable to climate change; record heatwaves and droughts have previously caused Tarbela dam to reach dead pool level and reduced its production by 62% in one year.
- Proposed hydropower tariffs in the pipeline (4-10 usc/KWh) are significantly more expensive than variable renewable energy sources like solar and wind, which average 4 usc/KWh.
- The report recommends shifting focus toward agile, modular solutions, including installing floating solar PV on existing reservoirs and incentivizing private rooftop solar to reduce reliance on large-scale hydro.
Cite the original document
- APA
- Isaad, H. (2022). To Build or Not to Build: Keeping Pakistan’s Hydropower Reliance in Check. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2022-09/IEEFA%20Report_To%20build%20or%20not%20to%20Build-Keeping%20Pakistan%27s%20Hydropower%20Reliance%20in%20Check-20220920.pdf
- Chicago
- Isaad, Haneea. To Build or Not to Build: Keeping Pakistan’s Hydropower Reliance in Check. Institute for Energy Economics and Financial Analysis, 2022. https://ieefa.org/sites/default/files/2022-09/IEEFA%20Report_To%20build%20or%20not%20to%20Build-Keeping%20Pakistan%27s%20Hydropower%20Reliance%20in%20Check-20220920.pdf.
- Wikipedia
- {{cite report |last1=Isaad |first1=Haneea |title=To Build or Not to Build: Keeping Pakistan’s Hydropower Reliance in Check |publisher=Institute for Energy Economics and Financial Analysis |date=September 2022 |url=https://ieefa.org/sites/default/files/2022-09/IEEFA%20Report_To%20build%20or%20not%20to%20Build-Keeping%20Pakistan%27s%20Hydropower%20Reliance%20in%20Check-20220920.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001416)}}
- BibTeX
- @techreport{isaad2022build, author = {Isaad, Haneea}, title = {{To Build or Not to Build: Keeping Pakistan’s Hydropower Reliance in Check}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2022}, month = sep, url = {https://ieefa.org/sites/default/files/2022-09/IEEFA%20Report_To%20build%20or%20not%20to%20Build-Keeping%20Pakistan%27s%20Hydropower%20Reliance%20in%20Check-20220920.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001416} }
Full text
Collected · Record updated