The report finds that while India issued a record 73 GW of renewable energy tenders in 2024, project realisation is hindered by a 'vicious cycle' of undersubscription, delays in signing power sale agreements, and high cancellation rates.
Key insights
- In 2024, India issued a record 73 GW of utility-scale renewable energy tenders, with non-vanilla technologies like wind-solar hybrid and energy storage accounting for nearly half of the issued capacity.
- Tender undersubscription increased significantly in 2024, with approximately 8.5 GW of capacity undersubscribed—five times the level seen in 2023. Energy storage systems (ESS), particularly firm and dispatchable renewable energy (FDRE) tenders, represent the largest share of this undersubscribed capacity at about 44%.
- There is a significant backlog of unsigned power sale agreements (PSAs), with cumulative unsigned capacity exceeding 40 GW. Tenders from the Solar Energy Corporation of India (SECI) alone account for about 12 GW of this unsigned capacity, with some solar tenders delayed by nearly five years.
- Between 2020 and 2024, 38.3 GW of utility-scale renewable energy capacity was cancelled, representing approximately 19% of the total issued capacity. Cancellations peaked in 2023, with ESS-based tenders accounting for two-thirds of the cancelled capacity.
- Standalone energy storage system (ESS) projects face severe bottlenecks; of the 30.8 GW capacity issued by 2024, approximately 22.4 GW has been cancelled or shelved due to novel tender designs, site selection issues for pumped hydro storage, and PSA/PPA signing delays.
- Project realisation challenges are expected to cumulatively affect 75 GW of utility-scale renewable energy capacity tendered by 2030, potentially deterring investor interest and affecting the availability of low-cost overseas financing.
- The report identifies a shift in market share from SECI-led tenders toward those directly invited by energy offtakers, as developers find that the absence of an intermediary agency leads to quicker PSA signings.
Cite the original document
- APA
- Institute for Energy Economics and Financial Analysis (n.d.). Challenges in India’s Tender-Driven Renewable Energy Market. https://ieefa.org/sites/default/files/2025-03/Challenges%20in%20India%E2%80%99s%20Tender-Driven%20Renewable%20Energy%20Market_March%202025.pdf
- Chicago
- Institute for Energy Economics and Financial Analysis. Challenges in India’s Tender-Driven Renewable Energy Market. n.d. https://ieefa.org/sites/default/files/2025-03/Challenges%20in%20India%E2%80%99s%20Tender-Driven%20Renewable%20Energy%20Market_March%202025.pdf.
- Wikipedia
- {{cite report |author=Institute for Energy Economics and Financial Analysis |title=Challenges in India’s Tender-Driven Renewable Energy Market |url=https://ieefa.org/sites/default/files/2025-03/Challenges%20in%20India%E2%80%99s%20Tender-Driven%20Renewable%20Energy%20Market_March%202025.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001081)}}
- BibTeX
- @techreport{instituteforenergyeconomicsandfinancialanalysisndchallenges, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{Challenges in India’s Tender-Driven Renewable Energy Market}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2025-03/Challenges%20in%20India%E2%80%99s%20Tender-Driven%20Renewable%20Energy%20Market_March%202025.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001081} }
Full text
Collected · Record updated