Bangladesh Power Development Board Financial Results FY2020-21
Summary
The Bangladesh Power Development Board (BPDB) is facing severe financial distress due to massive overcapacity and rising costs from independent power plants (IPPs) and imported fossil fuels. Operating losses doubled in FY2020-21, necessitating a record government subsidy of Tk117.8 billion. The report warns that continued expansion of coal and LNG-fired plants will exacerbate these losses and force significant tariff increases. It recommends that the new Integrated Energy and Power Master Plan (IEPMP) prioritize grid investment, energy efficiency, and ambitious renewable energy targets over further fossil fuel capacity.
Key insights
- The Bangladesh Power Development Board's (BPDB) operating loss doubled in FY2020-21, primarily due to a 58% increase in the cost of electricity purchases from independent power plants (IPPs). This resulted in a record government subsidy of Tk117.8 billion (US$1.4 billion) to cover the losses, up from Tk74.4 billion the previous year.
- For the first time, electricity purchases from IPPs account for over 50% of the BPDB's total operating expenses. A major driver of this cost is the Payra coal-fired power plant, where the BPDB pays Tk1.3 billion (US$15 million) monthly in capacity charges because one unit remains idle due to missing transmission infrastructure.
- Bangladesh is facing severe power overcapacity; overall plant utilisation was only 42% in FY2020-21. With 12,967MW under construction and 19,651MW planned by the end of FY2024-25, compared to only 3,990MW slated for retirement, utilisation could drop to 38% even if power generation grows by 12% annually.
- The shift toward imported liquefied natural gas (LNG) exposes Bangladesh to extreme price volatility, as seen in 2021 when spot prices surged past US$50/MMBtu. This volatility has led gas distributors to propose more than doubling gas tariffs, and the BPDB to propose bulk power tariff increases of up to 64%.
- The BPDB predicts that the government subsidy required for FY2021-22 may reach Tk200 billion, a 71% increase over the FY2020-21 record. The BPDB also estimates a potential shortfall of Tk325 billion (US$3.8 billion) if proposed tariff increases are not implemented.
- The report argues that the new Integrated Energy and Power Master Plan (IEPMP), funded by JICA, should avoid locking in reliance on imported LNG and coal. Instead, it should prioritize grid investments, energy efficiency, and the targets set in the Mujib Climate Prosperity Plan (30% renewables by 2030 and 40% by 2041) and SREDA's proposal for 10,000MW of renewables by 2030.
Cite the original document
- APA
- Nicholas, S. (2022). Bangladesh Power Development Board Financial Results FY2020-21. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/Bangladesh-Power-Development-Board-Financial-Results-FY2020_21_February-2022.pdf
- Chicago
- Nicholas, Simon. Bangladesh Power Development Board Financial Results FY2020-21. Institute for Energy Economics and Financial Analysis, 2022. https://ieefa.org/sites/default/files/resources/Bangladesh-Power-Development-Board-Financial-Results-FY2020_21_February-2022.pdf.
- Wikipedia
- {{cite report |last1=Nicholas |first1=Simon |title=Bangladesh Power Development Board Financial Results FY2020-21 |publisher=Institute for Energy Economics and Financial Analysis |date=February 2022 |url=https://ieefa.org/sites/default/files/resources/Bangladesh-Power-Development-Board-Financial-Results-FY2020_21_February-2022.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000970)}}
- BibTeX
- @techreport{nicholas2022bangladesh, author = {Nicholas, Simon}, title = {{Bangladesh Power Development Board Financial Results FY2020-21}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2022}, month = feb, url = {https://ieefa.org/sites/default/files/resources/Bangladesh-Power-Development-Board-Financial-Results-FY2020_21_February-2022.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000970} }
Full text
Collected · Record updated