Summary
The briefing argues that LNG Canada Phase 2 faces a materially different and riskier environment than Phase 1, characterized by higher construction costs, ownership instability, and an impending global LNG supply glut.
Key insights
- Phase 2 faces higher construction cost risks than Phase 1 because it cannot rely on the same lump-sum, fixed-payment contracts that insulated Phase 1 investors from inflation. Current indicators, such as Statistics Canada’s non-residential construction price index, show a cost base substantially higher than in 2018.
- A new commercial agreement for the Coastal GasLink (CGL) pipeline expansion increases the exposure of LNG Canada proponents to construction surprises, as TC Energy will now take a reduced role with limits on its capital commitments and liability for cost overruns.
- The project's ownership structure is becoming unstable at a critical time for capital raising; Petronas has already reduced its stake, and Shell and Mitsubishi are exploring options to sell their respective interests.
- Trade tensions between the U.S. and Canada, including tariffs of up to 50% on Canadian steel and aluminum, are increasing domestic production costs and creating uncertainty regarding the cost and availability of construction inputs.
- While the Canadian government's Major Projects Office (MPO) is fast-tracking Phase 2 as a project of national significance, this also increases competition for labor and contractors by accelerating other competing LNG projects.
- Phase 1's operational record, specifically the burning of over 350 million cubic metres of gas in its first year and non-compliance regarding black-smoke emissions, may weaken the social license and increase community scrutiny for Phase 2.
- Phase 2 enters the market during a projected global supply glut, with approximately 254 MTPA of new LNG export capacity expected between 2026 and 2030, which may lower prices and reduce the ability to secure long-term, fixed-volume contracts.
Cite the original document
- APA
- Kalegha, M. (2026). LNG Canada Phase 2: After FID key questions remain. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2026-09/09-29_LNG%20Canada%20Phase%202_September%202026.pdf
- Chicago
- Kalegha, Mark. LNG Canada Phase 2: After FID key questions remain. Institute for Energy Economics and Financial Analysis, 2026. https://ieefa.org/sites/default/files/2026-09/09-29_LNG%20Canada%20Phase%202_September%202026.pdf.
- Wikipedia
- {{cite report |last1=Kalegha |first1=Mark |title=LNG Canada Phase 2: After FID key questions remain |publisher=Institute for Energy Economics and Financial Analysis |date=September 2026 |url=https://ieefa.org/sites/default/files/2026-09/09-29_LNG%20Canada%20Phase%202_September%202026.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000888)}}
- BibTeX
- @techreport{kalegha2026lng, author = {Kalegha, Mark}, title = {{LNG Canada Phase 2: After FID key questions remain}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2026}, month = sep, url = {https://ieefa.org/sites/default/files/2026-09/09-29_LNG%20Canada%20Phase%202_September%202026.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000888} }
Full text
Collected · Record updated