The Puerto Rican government is planning to contract over 5,200 megawatts of power generation, which significantly exceeds the island's peak demand of less than 3,200 MW in 2024.
Key insights
- The Puerto Rican government is pursuing multiple procurement processes that could add more than 5,200 megawatts of power generation, representing a major overbuild of the centralized system compared to a 2024 peak demand of less than 3,200 MW.
- A specific procurement process for 3,000 megawatts of new generation, likely gas-fired, includes up to 600 MW to replace the Costa Sur power plant.
- The Financial Oversight and Management Board (FOMB) has raised concerns regarding structural and procedural issues in the contracting process, including port access, fuel infrastructure, and ratepayer affordability, but reports that its feedback has been ignored.
- The P3 Authority's procurement processes are occurring outside the integrated resource planning process and have been marred by a scandal where a contract for 400 MW of emergency generation was canceled after it was alleged that Power Expectations fraudulently signed on behalf of Enchanted Rock.
- Despite the government's focus on centralized fossil fuel generation, rooftop solar installations in Puerto Rico reached more than 1,600 MW by June 2026, marking a 28% year-over-year increase.
Cite the original document
- APA
- Kunkel, C. (2026). Puerto Rico government continues plan for major overbuilding of grid with fossil fuel-based sources. Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/puerto-rico-government-continues-plan-major-overbuilding-grid-fossil-fuel-based-sources
- Chicago
- Kunkel, Cathy. Puerto Rico government continues plan for major overbuilding of grid with fossil fuel-based sources. Institute for Energy Economics and Financial Analysis, 2026. https://ieefa.org/resources/puerto-rico-government-continues-plan-major-overbuilding-grid-fossil-fuel-based-sources.
- Wikipedia
- {{cite press release |last1=Kunkel |first1=Cathy |title=Puerto Rico government continues plan for major overbuilding of grid with fossil fuel-based sources |publisher=Institute for Energy Economics and Financial Analysis |date=10 September 2026 |url=https://ieefa.org/resources/puerto-rico-government-continues-plan-major-overbuilding-grid-fossil-fuel-based-sources |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000784)}}
- BibTeX
- @misc{kunkel2026puerto, author = {Kunkel, Cathy}, title = {{Puerto Rico government continues plan for major overbuilding of grid with fossil fuel-based sources}}, publisher = {Institute for Energy Economics and Financial Analysis}, year = {2026}, month = sep, url = {https://ieefa.org/resources/puerto-rico-government-continues-plan-major-overbuilding-grid-fossil-fuel-based-sources}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000784} }
Full text
Collected · Record updated