Risky and Over-Subsidised Financial Analysis: Rampal Power Plant
Summary
The IEEFA report argues that the Rampal Power Plant is a risky, over-subsidised project that will increase electricity rates in Bangladesh and should be replaced by commercially viable solar energy alternatives.
Key insights
- The Rampal plant is expected to increase electricity rates in Bangladesh, with revenue requirements necessitating tariffs 32% higher than the current average cost of production; without subsidies, these costs would be 62% higher.
- The project relies on three subsidies totaling more than US$3 billion: a 15-year income tax exemption worth US$936m, a below-market-rate loan from the Indian EXIM Bank worth US$988m, and an annual US$26m subsidy for maintenance dredging.
- The plant faces significant operational and financial risks, including potential stranded-asset status due to declining plant load factors (PLFs) in China, the U.S., and India, as well as vulnerability to storm surges due to its location in a "Wind risk zone".
- Solar energy is presented as a viable alternative, with Bangladesh possessing the potential to generate 380TWh of electricity per annum through solar PV; achieving a 10GW utility solar goal by 2025 would require only 0.15% of the country's land.
- The project poses specific risks to the Indian EXIM Bank, including risks to its international fund-raising capacity and refinance risk due to the coal-fired nature of the project.
Cite the original document
- APA
- Buckley, J. S. T. (2016). Risky and Over-Subsidised Financial Analysis: Rampal Power Plant. Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/risky-and-over-subsidised-financial-analysis-rampal-power-plant
- Chicago
- Buckley, Jai Sharda Tim. Risky and Over-Subsidised Financial Analysis: Rampal Power Plant. Institute for Energy Economics and Financial Analysis, 2016. https://ieefa.org/resources/risky-and-over-subsidised-financial-analysis-rampal-power-plant.
- Wikipedia
- {{cite report |last1=Buckley |first1=Jai Sharda Tim |title=Risky and Over-Subsidised Financial Analysis: Rampal Power Plant |publisher=Institute for Energy Economics and Financial Analysis |date=1 June 2016 |url=https://ieefa.org/resources/risky-and-over-subsidised-financial-analysis-rampal-power-plant |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000760)}}
- BibTeX
- @techreport{buckley2016risky, author = {Buckley, Jai Sharda Tim}, title = {{Risky and Over-Subsidised Financial Analysis: Rampal Power Plant}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2016}, month = jun, url = {https://ieefa.org/resources/risky-and-over-subsidised-financial-analysis-rampal-power-plant}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000760} }
Full text
Collected · Record updated