European Pressurized Reactors (EPRs): Next Generation Design Suffers Old Problems
Summary
The European Pressurized Reactor (EPR) design has consistently suffered from massive cost overruns and construction delays across multiple countries. This trend suggests that nuclear energy is becoming a costly and risky alternative compared to the plummeting costs of solar and wind power.
Key insights
- Four out of five European Pressurized Reactors (EPRs) built or under construction have experienced significant construction delays or enormous cost overruns. Specific examples include the Olkiluoto 3 reactor in Finland, which was delayed by 17 years, and the Hinkley Point C reactor in the UK, which is already one-third over its original budget and delayed by at least two years.
- The EPR design contradicts the engineering axiom that subsequent iterations of a product become cheaper and faster to build; instead, it aligns with a 2020 MIT analysis finding that new nuclear designs often cost more than original projects.
- Nuclear energy's overnight construction costs are significantly higher than those of renewables. The U.S. Energy Information Administration (EIA) estimated nuclear reactor costs at USD$6,695 per kilowatt (kW), compared to USD$1,718/kW for onshore wind, USD$4,833/kW for offshore wind, and USD$1,748/kW for solar-plus-storage.
- While the costs of utility-scale solar and land-based wind fell by 88% and 68% respectively between 2010 and 2021, nuclear energy costs rose by almost 33% between 2015 and 2020.
- Due to high costs and the falling price of renewables, expensive nuclear facilities risk becoming stranded assets before their projected 60 to 80 year lifespans end.
Cite the original document
- APA
- Bass, F. (2023). European Pressurized Reactors (EPRs): Next Generation Design Suffers Old Problems. Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/european-pressurized-reactors-eprs-next-generation-design-suffers-old-problems
- Chicago
- Bass, Frank. European Pressurized Reactors (EPRs): Next Generation Design Suffers Old Problems. Institute for Energy Economics and Financial Analysis, 2023. https://ieefa.org/resources/european-pressurized-reactors-eprs-next-generation-design-suffers-old-problems.
- Wikipedia
- {{cite report |last1=Bass |first1=Frank |title=European Pressurized Reactors (EPRs): Next Generation Design Suffers Old Problems |publisher=Institute for Energy Economics and Financial Analysis |date=2 February 2023 |url=https://ieefa.org/resources/european-pressurized-reactors-eprs-next-generation-design-suffers-old-problems |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000390)}}
- BibTeX
- @techreport{bass2023european, author = {Bass, Frank}, title = {{European Pressurized Reactors (EPRs): Next Generation Design Suffers Old Problems}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2023}, month = feb, url = {https://ieefa.org/resources/european-pressurized-reactors-eprs-next-generation-design-suffers-old-problems}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000390} }
Full text
Collected · Record updated