Handlungsempfehlungen vom BESTGRID-Projekt Handbuch
Summary
The document argues that early, transparent public participation and a clear distinction between needs planning and corridor planning are essential to resolve conflicts and increase the legitimacy of the European energy transition's grid expansion.
Key insights
- The planning of high-voltage power lines is divided into two distinct levels: needs planning (Bedarfsplanung), which determines the necessity of lines based on scenarios, and corridor/route planning (Korridor- und Trassenplanung), which determines the specific path.
- A 'participation paradox' exists where the greatest opportunity for influence occurs at the start of the process (needs planning), but many stakeholders only realize they are affected during the later stages (corridor planning) when influence is significantly reduced.
- Effective public participation should follow a five-stage approach: stakeholder mapping, a tailored transparency strategy, implementation, documentation with feedback, and evaluation.
- High-voltage overhead lines are the global standard due to technical and economic reasons; underground cabling is significantly more expensive, often by a multiple, especially for alternating current (AC) at high voltage levels.
- The SüdLink project in Germany demonstrated that even with extensive citizen dialogue, local opposition can persist if stakeholders perceive a pre-determination of the preferred corridor, leading to demands for more transparent criteria and alternative technology assessments.
- The Stevin project in Belgium showed that despite intensive preparation and informal dialogue, a lack of transparent reasoning for rejecting proposed route alternatives can lead to extensive protests and legal delays.
- For transnational subsea cable projects like NemoLink, planners must navigate two different legal systems and coordinate stakeholder engagement across different countries to accelerate the permitting process.
- To mitigate health concerns regarding electromagnetic fields (EMF), transmission operators are encouraged to conduct on-site measurements under existing lines and involve independent experts from universities or research institutions.
- Environmental impacts of power lines differ by technology: overhead lines pose a collision risk for birds, particularly on thin shield wires, while underground cables affect soil conditions and soil-dwelling species.
Cite the original document
- APA
- Germanwatch (n.d.). Handlungsempfehlungen vom BESTGRID-Projekt Handbuch. https://www.germanwatch.org/sites/default/files/publication/11713.pdf
- Chicago
- Germanwatch. Handlungsempfehlungen vom BESTGRID-Projekt Handbuch. n.d. https://www.germanwatch.org/sites/default/files/publication/11713.pdf.
- Wikipedia
- {{cite report |author=Germanwatch |title=Handlungsempfehlungen vom BESTGRID-Projekt Handbuch |url=https://www.germanwatch.org/sites/default/files/publication/11713.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document gerwat-000733)}}
- BibTeX
- @techreport{germanwatchndhandlungsempfehlungen, author = {{Germanwatch}}, title = {{Handlungsempfehlungen vom BESTGRID-Projekt Handbuch}}, institution = {Germanwatch}, url = {https://www.germanwatch.org/sites/default/files/publication/11713.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document gerwat-000733} }
Full text
Collected · Record updated