Caso: Chile Temuco 2022
Summary
The document details the attempt by WTE Araucanía SPA to install a waste incinerator in Lautaro, Chile, designed to process 200,000 tonnes of waste annually and generate 14 MW of electricity. Despite an investment proposal of USD 80 million, the project was rejected by the Araucanía region's Environmental Evaluation Commission after a process spanning 2017 to 2022. The rejection was supported by over 17,000 citizen observations and the advocacy of the Environmental Rights Action Network (RADA), who argued the project contradicted national waste policies, lacked indigenous consultation, and threatened to turn Lautaro into a 'sacrifice zone'.
Key insights
- The proposed incineration project by WTE Araucanía SPA aimed to treat 200,000 tonnes of waste per year with an investment cost of USD 80 million, intending to generate 14 MW of electricity, with 12 MW to be sold to the National Electricity System (SEN).
- The project was rejected by the Environmental Evaluation Commission of the Araucanía region following a process from 2017 to 2022, which was marked by several irregularities: the absence of indigenous consultation, the unauthorized acceptance of a third addendum, and the fact that Lautaro's regulatory plan prohibits waste treatment stations at the proposed site.
- The incinerator was found to contradict multiple Chilean environmental policies, including the National Integrated Solid Waste Management Policy and the Regional Waste Policy 2030, because it lacked separation stages for recyclables and compostables, meaning all waste—including high-calorific recyclables—would be burned.
- The project conflicted with the Extended Producer Responsibility Law and the National Organic Waste Strategy (ENRO); the latter aims for 66% recovery of municipal organic waste by 2040 through composting and biodigestion, whereas the project proposed incineration for waste that is 49.6% to over 60% organic matter.
- Community resistance was led by the Environmental Rights Action Network (RADA), which provided technical assistance and environmental education to reveal the project's impacts, resulting in more than 17,000 formal observations against the proposal.
Cite the original document
- APA
- Global Alliance for Incinerator Alternatives (2022). Caso: Chile Temuco 2022. https://www.no-burn.org/wp-content/uploads/2023/04/PO-Temuco-Chile.pdf
- Chicago
- Global Alliance for Incinerator Alternatives. Caso: Chile Temuco 2022. 2022. https://www.no-burn.org/wp-content/uploads/2023/04/PO-Temuco-Chile.pdf.
- Wikipedia
- {{cite report |author=Global Alliance for Incinerator Alternatives |title=Caso: Chile Temuco 2022 |date=September 2022 |url=https://www.no-burn.org/wp-content/uploads/2023/04/PO-Temuco-Chile.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document gaia-000580)}}
- BibTeX
- @techreport{globalallianceforincineratoralternatives2022caso, author = {{Global Alliance for Incinerator Alternatives}}, title = {{Caso: Chile Temuco 2022}}, institution = {Global Alliance for Incinerator Alternatives}, year = {2022}, month = sep, url = {https://www.no-burn.org/wp-content/uploads/2023/04/PO-Temuco-Chile.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document gaia-000580} }
Full text
Collected · Record updated