National Nuclear Power Development Programme – Planning and Procurement of 9.6GW of nuclear power stations
Summary
This submission by Earthlife Africa and SAFCEI contends that South Africa's 9.6GW nuclear procurement plan is based on flawed data and unrealistic costs, potentially leading to a financial catastrophe for taxpayers and electricity users.
Key insights
- The estimated construction costs for nuclear power in the updated Integrated Resource Plan (IRP) of $5,800/kW are considered unrealistic, as current international estimates are approximately $8,000/kW.
- The IRP's assumed lifetime load factor of 92% is described as unprecedented worldwide and significantly higher than the actual lifetime load factors of the Koeberg reactors, which are below 70%.
- The procurement of 9.6GW of nuclear power stations is estimated to cost between R400 billion and R1 trillion.
- The decision to commit to 9,600 MW of nuclear capacity was not a result of the Integrated Resource Planning (IRP) process but was instead imposed upon it by the government.
- The 2008 call for tenders for nuclear capacity failed because the lowest bids received, reported to be around $6,000/kW, were too high to be financeable.
- The document asserts that the planning and legislative framework for nuclear procurement is incomplete, noting that the Draft 2012 Integrated Energy Plan has not been finalised and the enabling provisions of the National Energy Act have not commenced.
- The cost of capital used in the IRP (8%) is the same for all options, which fails to account for the fact that nuclear power is the most economically risky generation option.
- There is a significant risk regarding decommissioning and waste disposal costs, as the IRP does not explicitly require segregated funds, potentially leaving future generations to bear the financial burden.
- The European Pressurised Water Reactor (EPR) design has a poor track record of delivery, with projects in Finland and France running 4-6 years late and costing at least double the original estimates.
Cite the original document
- APA
- Pole, A. L. (2015). National Nuclear Power Development Programme – Planning and Procurement of 9.6GW of nuclear power stations. Earthlife Africa. https://earthlife.org.za/wp-content/uploads/2020/06/ELA-JHB-SAFCEI-Letter-to-the-Minister-Finance-10-February-2015.pdf
- Chicago
- Pole, Adrian Leonard. National Nuclear Power Development Programme – Planning and Procurement of 9.6GW of nuclear power stations. Earthlife Africa, 2015. https://earthlife.org.za/wp-content/uploads/2020/06/ELA-JHB-SAFCEI-Letter-to-the-Minister-Finance-10-February-2015.pdf.
- Wikipedia
- {{cite press release |last1=Pole |first1=Adrian Leonard |title=National Nuclear Power Development Programme – Planning and Procurement of 9.6GW of nuclear power stations |publisher=Earthlife Africa |date=10 February 2015 |url=https://earthlife.org.za/wp-content/uploads/2020/06/ELA-JHB-SAFCEI-Letter-to-the-Minister-Finance-10-February-2015.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document earthli-000031)}}
- BibTeX
- @misc{pole2015national, author = {Pole, Adrian Leonard}, title = {{National Nuclear Power Development Programme – Planning and Procurement of 9.6GW of nuclear power stations}}, publisher = {Earthlife Africa}, year = {2015}, month = feb, url = {https://earthlife.org.za/wp-content/uploads/2020/06/ELA-JHB-SAFCEI-Letter-to-the-Minister-Finance-10-February-2015.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document earthli-000031} }
Full text
Collected · Record updated