N O N E W C O A L B Y 2 0 2 1 : T H E C O L L A P S E O F T H E G L O B A L C O A L P I P E L I N E
Summary
Since 2015, South-East Asia's pre-construction coal pipeline has decreased by 63%, from 134GW to 49GW, with 102GW of projects cancelled compared to 33GW that entered operation. Malaysia has emerged as the region's first 'no new coal' nation via its Energy Transition Plan 2021-2040, while the Philippines has implemented a moratorium on new coal permits. Indonesia has announced a stop to new coal plants after 2023, though over 100 projects may still be exempt. Viet Nam's draft Eighth Power Development Plan (PDP8) limits new coal to projects under construction or planned for completion by 2025. Conversely, Laos, Thailand, and Cambodia are identified as laggards, with Laos maintaining the world's seventh largest pre-construction pipeline at 6.7GW.
Key insights
- South-East Asia's pipeline of proposed coal power plants has shrunk by 63% since 2015, falling from 134GW to 49GW. This represents a 3.1:1 ratio of cancelled projects (102GW) to those that became operational (33GW). The remaining 49GW pipeline constitutes 16% of the global total and 42% of the non-OECD pipeline.
- Malaysia is the first nation in South-East Asia to commit to 'no new coal', a position formalised in its Energy Transition Plan 2021-2040 launched in June 2021. This follows a commitment from the utility TNB to cease new coal-fired power construction, shifting the national policy focus toward retiring the existing fleet during the 2030s.
- The Philippines has seen its pre-construction coal pipeline drop by 65% since July 2020, supported by an October 2020 Energy Ministry moratorium on new coal-fired power project permits and a commitment to increase renewable energy capacity.
- Indonesia intends to stop building new coal plants after 2023 and has pledged to be net zero by 2060. However, analysis indicates that over 100 projects may be excluded from this commitment, potentially adding nearly 35GW of capacity to the operating fleet.
- Viet Nam's pre-construction coal pipeline of 19.4GW is the third largest globally, though it has cancelled 33GW since 2015. The draft Eighth Power Development Plan (PDP8) restricts new coal to plants already under construction or planned for completion by 2025, though it still projects up to 17GW of coal coming online in the next decade.
- Laos, Thailand, and Cambodia have not formally moved away from coal. Laos possesses the world's seventh largest pre-construction pipeline at 6.7GW. Thailand and Cambodia have smaller remaining pipelines of 655MW and 700MW, respectively.
Cite the original document
- APA
- E3G (n.d.). N O N E W C O A L B Y 2 0 2 1 : T H E C O L L A P S E O F T H E G L O B A L C O A L P I P E L I N E. https://www.e3g.org/wp-content/uploads/No-New-Coal-by-2021-5.-South-East-Asia.pdf
- Chicago
- E3G. N O N E W C O A L B Y 2 0 2 1 : T H E C O L L A P S E O F T H E G L O B A L C O A L P I P E L I N E. n.d. https://www.e3g.org/wp-content/uploads/No-New-Coal-by-2021-5.-South-East-Asia.pdf.
- Wikipedia
- {{cite report |author=E3G |title=N O N E W C O A L B Y 2 0 2 1 : T H E C O L L A P S E O F T H E G L O B A L C O A L P I P E L I N E |url=https://www.e3g.org/wp-content/uploads/No-New-Coal-by-2021-5.-South-East-Asia.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document e3g-001292)}}
- BibTeX
- @techreport{e3gnd, author = {{E3G}}, title = {{N O N E W C O A L B Y 2 0 2 1 : T H E C O L L A P S E O F T H E G L O B A L C O A L P I P E L I N E}}, institution = {E3G}, url = {https://www.e3g.org/wp-content/uploads/No-New-Coal-by-2021-5.-South-East-Asia.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document e3g-001292} }
Full text
Collected · Record updated