Summary
The report finds that Scotland's onshore wind workforce must increase from approximately 6,900 FTE in 2024 to a peak of 20,500 FTE in 2027 to meet 2030 capacity targets, facing severe risks from critical shortages in high voltage engineers and wind turbine technicians.
Key insights
- To achieve the 2030 ambition, the onshore wind workforce in Scotland needs to grow from around 6,900 full-time equivalent (FTE) positions in 2024 to a peak of approximately 20,500 FTE in 2027, with over 90% of these roles concentrated in construction and installation.
- Severe skill shortages are likely to jeopardize the goal of installing 20 GW of onshore wind by 2030. By 2027, the demand for construction and installation FTEs is predicted to be four times higher than in 2024, with a five-fold increase required for civil contractors.
- Critical technical shortages exist for high voltage engineers and wind turbine technicians. FTEs for electricity grid connections must rise from 1,100 in 2024 to 4,500 in 2027 (a 400% increase), while wind turbine technician FTEs need to grow from 465 in 2024 to nearly 1,200 by 2030 (a 258% increase).
- Workforce demand is heavily concentrated geographically; more than 46% of construction and installation roles and approximately 37% of operations and maintenance (O&M) roles from 2027 onwards will be required in the Highland and Dumfries and Galloway regions.
- There is a persistent scarcity of skilled planners and specialist environmental consultants, with an estimated annual requirement of 100 FTE planners and 434 FTE environmental consultants across Scotland between 2024 and 2030.
- The sector faces increasing demand for digital skills, specifically for data analysis of sensor systems and the use of drones for visual inspections of turbine blades and nacelles to improve performance monitoring and reduce downtime.
- Competition for skilled workers is high, with 59% of stakeholders reporting significant competition for experienced staff and 41% for skilled staff in general. Higher salaries in the offshore wind sector attract younger workers away from onshore wind.
- There is a strategic opportunity to expand Scotland's remanufacturing capacity for turbine components, as increasing lead times for new parts from original equipment manufacturers (OEMs) leave some turbines idle.
- The current training capacity is insufficient; the Wind Training Network, comprising 11 further education institutions, only delivers between 70 and 80 trained individuals per year, which is deemed too small to significantly impact the forecast demand.
Cite the original document
- APA
- ClimateXChange (2024). Mapping the current and future workforce and skills requirements in Scotland’s onshore wind industry. https://www.climatexchange.org.uk/publications/mapping-the-current-and-future-workforce-and-skills-requirements-in-scotlands-onshore-wind-industry/
- Chicago
- ClimateXChange. Mapping the current and future workforce and skills requirements in Scotland’s onshore wind industry. 2024. https://www.climatexchange.org.uk/publications/mapping-the-current-and-future-workforce-and-skills-requirements-in-scotlands-onshore-wind-industry/.
- Wikipedia
- {{cite report |author=ClimateXChange |title=Mapping the current and future workforce and skills requirements in Scotland’s onshore wind industry |date=13 May 2024 |url=https://www.climatexchange.org.uk/publications/mapping-the-current-and-future-workforce-and-skills-requirements-in-scotlands-onshore-wind-industry/ |access-date=5 November 2026 |via=Climate Insights Directory (document climex-000127)}}
- BibTeX
- @techreport{climatexchange2024mapping, author = {{ClimateXChange}}, title = {{Mapping the current and future workforce and skills requirements in Scotland’s onshore wind industry}}, institution = {ClimateXChange}, year = {2024}, month = may, url = {https://www.climatexchange.org.uk/publications/mapping-the-current-and-future-workforce-and-skills-requirements-in-scotlands-onshore-wind-industry/}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document climex-000127} }
Full text
Collected · Record updated