Estimating the costs and impact of decarbonising heat in the public sector

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The report estimates that decarbonising heat in Scotland's public sector buildings by 2045 will require an investment between £3.3 billion and £8.8 billion, with a medium estimate of £6.1 billion.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The total investment required to decarbonise the public sector by 2045 is estimated to range from £3.3 billion to £8.8 billion, with a medium estimate of £6.1 billion.
  • Targeting the largest 10% of buildings by heat demand is a highly cost-effective strategy, as they account for 37% of total carbon emissions and could be decarbonised for an estimated £2 billion.
  • Air Source Heat Pumps (ASHP) are the dominant technology by cost, with an estimated medium cost of £4.8 billion, followed by heat network connections at £761 million and Ground Source Heat Pumps (GSHP) at £441 million.
  • A significant portion of the investment is concentrated in specific building categories: 63% of the investment is estimated to be in urban environments, and 47% of costs are associated with buildings constructed before 1919.
  • The education sector represents the largest decarbonisation requirement by floor area, with 80% of its area requiring an upgrade.
  • Stakeholders identified critical barriers to delivery, including a lack of a central database for public sector buildings, insufficient staff capacity and technical skills, and limited availability of a mature supply chain.
  • Funding and finance are the most prominent challenges, with issues including restrictive annual budget cycles that prevent carrying funds over, complex public funding application processes, and high upfront capital costs.
  • Grid capacity and Distribution Network Operator (DNO) costs are significant barriers, with some projects experiencing connection costs ranging from £3,000 to £100,000 and lengthy lead times for increased supply.
  • Operational constraints, particularly in healthcare and education, limit the timing of works; for example, school upgrades are often restricted to summer holidays, which are deemed insufficient for the scale of work required by 2045.
  • Heat networks are viewed as a potential solution for large sites and urban areas, but their implementation is hindered by a lack of procurement experience for 'heat purchase agreements' and infrastructure challenges.

Cite the original document

APA
H., W., B., H., N., G., V., H., B., S., & D., K. (2026). Estimating the costs and impact of decarbonising heat in the public sector. ClimateXChange. https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/
Chicago
H., Waheed,, Hartfield, B., Green, N., Hunt, V., Sandles, B., and King, D. Estimating the costs and impact of decarbonising heat in the public sector. ClimateXChange, 2026. https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/.
Wikipedia
{{cite report |last1=H. |first1=Waheed, |last2=B. |first2=Hartfield, |last3=N. |first3=Green, |last4=V. |first4=Hunt, |last5=B. |first5=Sandles, |last6=D. |first6=King, |title=Estimating the costs and impact of decarbonising heat in the public sector |publisher=ClimateXChange |date=4 September 2026 |url=https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/ |access-date=5 November 2026 |via=Climate Insights Directory (document climex-000092)}}
BibTeX
@techreport{h2026estimating, author = {H., Waheed, and B., Hartfield, and N., Green, and V., Hunt, and B., Sandles, and D., King,}, title = {{Estimating the costs and impact of decarbonising heat in the public sector}}, institution = {ClimateXChange}, year = {2026}, month = sep, url = {https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document climex-000092} }