Estimating the costs and impact of decarbonising heat in the public sector
Summary
The report estimates that decarbonising heat in Scotland's public sector buildings by 2045 will require an investment between £3.3 billion and £8.8 billion, with a medium estimate of £6.1 billion.
Key insights
- The total investment required to decarbonise the public sector by 2045 is estimated to range from £3.3 billion to £8.8 billion, with a medium estimate of £6.1 billion.
- Targeting the largest 10% of buildings by heat demand is a highly cost-effective strategy, as they account for 37% of total carbon emissions and could be decarbonised for an estimated £2 billion.
- Air Source Heat Pumps (ASHP) are the dominant technology by cost, with an estimated medium cost of £4.8 billion, followed by heat network connections at £761 million and Ground Source Heat Pumps (GSHP) at £441 million.
- A significant portion of the investment is concentrated in specific building categories: 63% of the investment is estimated to be in urban environments, and 47% of costs are associated with buildings constructed before 1919.
- The education sector represents the largest decarbonisation requirement by floor area, with 80% of its area requiring an upgrade.
- Stakeholders identified critical barriers to delivery, including a lack of a central database for public sector buildings, insufficient staff capacity and technical skills, and limited availability of a mature supply chain.
- Funding and finance are the most prominent challenges, with issues including restrictive annual budget cycles that prevent carrying funds over, complex public funding application processes, and high upfront capital costs.
- Grid capacity and Distribution Network Operator (DNO) costs are significant barriers, with some projects experiencing connection costs ranging from £3,000 to £100,000 and lengthy lead times for increased supply.
- Operational constraints, particularly in healthcare and education, limit the timing of works; for example, school upgrades are often restricted to summer holidays, which are deemed insufficient for the scale of work required by 2045.
- Heat networks are viewed as a potential solution for large sites and urban areas, but their implementation is hindered by a lack of procurement experience for 'heat purchase agreements' and infrastructure challenges.
Cite the original document
- APA
- H., W., B., H., N., G., V., H., B., S., & D., K. (2026). Estimating the costs and impact of decarbonising heat in the public sector. ClimateXChange. https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/
- Chicago
- H., Waheed,, Hartfield, B., Green, N., Hunt, V., Sandles, B., and King, D. Estimating the costs and impact of decarbonising heat in the public sector. ClimateXChange, 2026. https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/.
- Wikipedia
- {{cite report |last1=H. |first1=Waheed, |last2=B. |first2=Hartfield, |last3=N. |first3=Green, |last4=V. |first4=Hunt, |last5=B. |first5=Sandles, |last6=D. |first6=King, |title=Estimating the costs and impact of decarbonising heat in the public sector |publisher=ClimateXChange |date=4 September 2026 |url=https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/ |access-date=5 November 2026 |via=Climate Insights Directory (document climex-000092)}}
- BibTeX
- @techreport{h2026estimating, author = {H., Waheed, and B., Hartfield, and N., Green, and V., Hunt, and B., Sandles, and D., King,}, title = {{Estimating the costs and impact of decarbonising heat in the public sector}}, institution = {ClimateXChange}, year = {2026}, month = sep, url = {https://www.climatexchange.org.uk/publications/estimating-the-costs-and-impact-of-decarbonising-heat-in-the-public-sector/}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document climex-000092} }
Full text
Collected · Record updated