A letter from the South African Department of Environmental Affairs to Eskom regarding the Matimba Power Station's application for postponement of compliance with the National Environmental Management: Air Quality Act 39 of 2004 minimum emission standards.
Key insights
- A postponement of compliance with the minimum emission standard for new plants is granted for the period from 1 April 2020 to 31 March 2025, with a limit of 3500mg/Nm3 based on the sulphur content of the fuel. The facility must achieve a limit of 500mg/Nm3 by 01 April 2025, citing the station's contribution to the SO2 pollution load in the Waterberg-Bojanala Priority Area and the fact that the station is not scheduled for decommissioning.
- No decision was made regarding NOx standards as no application was submitted; therefore, the requirement to comply with minimum emission standards for existing plants remains in effect.
Cite the original document
- APA
- Centre for Environmental Rights (n.d.). KM_C554e-20150213193422. https://cer.org.za/wp-content/uploads/2015/02/Matimba-Letter.pdf?x21779
- Chicago
- Centre for Environmental Rights. KM_C554e-20150213193422. n.d. https://cer.org.za/wp-content/uploads/2015/02/Matimba-Letter.pdf?x21779.
- Wikipedia
- {{cite press release |author=Centre for Environmental Rights |title=KM_C554e-20150213193422 |url=https://cer.org.za/wp-content/uploads/2015/02/Matimba-Letter.pdf?x21779 |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @misc{centreforenvironmentalrightsndkmc554e20150213193422, author = {{Centre for Environmental Rights}}, title = {{KM\_C554e-20150213193422}}, publisher = {Centre for Environmental Rights}, url = {https://cer.org.za/wp-content/uploads/2015/02/Matimba-Letter.pdf?x21779}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated