Assessment of the Need for the proposed Karpowership Power Plant projects
Summary
The report argues that the proposed 1.2 GW Karpowership gas power plants are not aligned with a least-cost investment pathway for South Africa. Drawing on a study by Meridian Economics and the CSIR, it finds that the grid should prioritize rapid renewable energy build-out and storage, with new gas capacity not being economically optimal until the mid-2030s. The document concludes that commissioning these plants by 2022 would create an unnecessary economic burden for ratepayers and that the procurement process (RMIPP) was biased against renewable energy options.
Key insights
- The proposed Karpowership projects, totaling 1.2 GW of gas-based capacity, are neither timely nor economically optimal, as they would come online up to 13 years before the economically optimal addition of non-peaking gas capacity.
- Commissioning the Karpowerships risks creating a long-term financial burden for South African ratepayers due to a proposed 20-year power purchase agreement for capacity that may be under-utilized or undercut by cheaper renewables.
- The Risk Mitigation Independent Power Producer Procurement Programme (RMIPP) process was likely biased toward fossil fuels because it required bidders to guarantee dispatchability from 08:00 to 21:30, which precluded variable renewable energy options.
- A least-cost optimization suggests that South Africa should prioritize building renewables in areas with existing transmission capacity, such as Mpumalanga and Northern Free-State, while expanding infrastructure to other optimal resource locations.
- Existing diesel generators can sufficiently meet peaking demand requirements for the next decade, removing the immediate need for new gas-fired peaking plants.
Cite the original document
- APA
- Centre for Environmental Rights (n.d.). Assessment of the Need for the proposed Karpowership Power Plant projects. https://cer.org.za/wp-content/uploads/2021/08/Annexure-AJ2-RMI-Report-27.07.2021.pdf?x21779
- Chicago
- Centre for Environmental Rights. Assessment of the Need for the proposed Karpowership Power Plant projects. n.d. https://cer.org.za/wp-content/uploads/2021/08/Annexure-AJ2-RMI-Report-27.07.2021.pdf?x21779.
- Wikipedia
- {{cite report |author=Centre for Environmental Rights |title=Assessment of the Need for the proposed Karpowership Power Plant projects |url=https://cer.org.za/wp-content/uploads/2021/08/Annexure-AJ2-RMI-Report-27.07.2021.pdf?x21779 |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @techreport{centreforenvironmentalrightsndassessment, author = {{Centre for Environmental Rights}}, title = {{Assessment of the Need for the proposed Karpowership Power Plant projects}}, institution = {Centre for Environmental Rights}, url = {https://cer.org.za/wp-content/uploads/2021/08/Annexure-AJ2-RMI-Report-27.07.2021.pdf?x21779}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated