A CASE STUDY OF WORLD BANK SUPPORTED WATER PROJECTS IN EKITI, RIVERS, AND BAUCHI STATES
Summary
The report finds that World Bank-funded water reforms in Nigeria have failed to provide reliable public water access, instead promoting a corporatisation model that prioritises financial viability and profit over the human right to water.
Key insights
- The Third National Urban Water Sector Reform Program (NUWSRP3), funded by a $250 million loan, failed to achieve its goals of increasing water access in Ekiti, Rivers, and Bauchi States, with the World Bank's own audit rating the program as 'Moderately Unsatisfactory'.
- In Ekiti State, the project failed to deliver promised benefits; 40% of survey respondents reported they had never received public water in their lifetimes, contradicting World Bank claims that 161,104 residents in the state benefited.
- The World Bank's intervention in Rivers State was a failure due to poor coordination with the African Development Bank (AfDB) and severe procurement delays, leading the World Bank to withdraw its investment in 2020 and the state government to return approximately $30 million.
- In Bauchi State, water distribution remains erratic and is often rationed to only one or two days a week due to power shortages and inadequate government funding, despite infrastructure renovations at the Warinje Dam.
- A critical systemic failure is the reliance on an unstable national electricity grid; water dams in Ekiti require 24 hours of uninterrupted power to operate effectively, a threshold that has never been met.
- The NUWSRP3 promoted a 'cost-recovery' model that shifted water from a public good to an economic commodity, leading to higher tariffs and the installation of prepaid meters in Ekiti that required installation fees of N5,000 and monthly payments of at least N2,000, often without any water being delivered.
- The report argues that the World Bank uses Investment Project Financing (IPF) to create an institutional framework that makes the privatisation and corporatisation of public utilities inevitable, as seen in Ekiti where the State Water Corporation was dissolved in 2022 and replaced by a corporate entity under the Companies and Allied Matters Act (CAMA).
- Nigeria's external debt to the International Development Association (IDA) reached $17.1 billion as of September 2024, contributing to a cycle where debt servicing exceeds the combined national budget for health, education, and infrastructure.
Cite the original document
- APA
- Corporate Accountability and Public Participation Africa (n.d.). A CASE STUDY OF WORLD BANK SUPPORTED WATER PROJECTS IN EKITI, RIVERS, AND BAUCHI STATES. https://cappaafrica.org/wp-content/uploads/2025/03/Report-Big-Debt-Big-Thirst-.pdf
- Chicago
- Corporate Accountability and Public Participation Africa. A CASE STUDY OF WORLD BANK SUPPORTED WATER PROJECTS IN EKITI, RIVERS, AND BAUCHI STATES. n.d. https://cappaafrica.org/wp-content/uploads/2025/03/Report-Big-Debt-Big-Thirst-.pdf.
- Wikipedia
- {{cite report |author=Corporate Accountability and Public Participation Africa |title=A CASE STUDY OF WORLD BANK SUPPORTED WATER PROJECTS IN EKITI, RIVERS, AND BAUCHI STATES |url=https://cappaafrica.org/wp-content/uploads/2025/03/Report-Big-Debt-Big-Thirst-.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document cappaaf-000088)}}
- BibTeX
- @techreport{corporateaccountabilityandpublicparticipationafricandcase, author = {{Corporate Accountability and Public Participation Africa}}, title = {{A CASE STUDY OF WORLD BANK SUPPORTED WATER PROJECTS IN EKITI, RIVERS, AND BAUCHI STATES}}, institution = {Corporate Accountability and Public Participation Africa}, url = {https://cappaafrica.org/wp-content/uploads/2025/03/Report-Big-Debt-Big-Thirst-.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document cappaaf-000088} }
Full text
Collected · Record updated