The Tracka Report 2021 reveals systemic failures in Nigeria's public project delivery, finding that many Zonal Intervention Projects are abandoned, poorly executed with substandard materials, or lack specified locations, hindering citizen oversight.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • Between January 2020 and June 2021, Tracka monitored 1,439 Zonal Intervention Projects, of which 662 were completed, 111 were ongoing, 268 had not started, 21 were abandoned, and 357 had unspecified locations.
  • Of the 1,626 Federal Consolidated Projects tracked during the same period, 646 were completed, 316 were ongoing, 335 had not started, 112 were abandoned, and 417 had unspecified locations.
  • Budgetary transparency is severely limited by the use of technical jargon and the omission of precise project locations, which prevents citizens and auditing bodies from monitoring implementation. For example, over 22 project line items in the 2020 Zonal Intervention Projects list, worth over N21 billion, had unknown locations.
  • There is a widespread use of substandard materials in public works, leading to rapid deterioration. In Edo state, a N65m road and gutter project in the Akoko-Edo Federal Constituency was so poor that citizens could peel the materials with their bare hands because it lacked iron rods and drainage.
  • Empowerment grants are often distributed as direct cash payments rather than bank transfers, making them opaque and unverifiable. In Bayelsa, youths in the East Senatorial District received undisclosed amounts of money in envelopes.
  • Projects are frequently assigned to agencies that lack the relevant mandate or capacity to execute them, such as the National Human Rights Commission being tasked with youth and women enterprise management in Akwa Ibom, or a Federal Medical Centre overseeing the construction of a town hall in Abia state.
  • Many projects are reported as completed by lawmakers despite evidence from residents and site visits that they remain unexecuted or incomplete. In Bauchi, a lawmaker claimed a maternal and child health clinic in Gungura was 100% completed, while residents insisted it remained undone.
  • Project maintenance is largely ignored, leading to the failure of completed infrastructure. In the Federal Capital Territory, ten solar-powered boreholes stopped working due to poor maintenance despite being completed.

Cite the original document

APA
Gheawe, G., Ievbooje, U., Adejola, A., Ladipe, A., & Adeniyi, S. (2021). TRACKA REPORT 2021. BudgIT. https://budgit.org/wp-content/uploads/2022/12/Trackas-Report.pdf
Chicago
Gheawe, Gabriel, Uadamen Ievbooje, Adewole Adejola, Ayomide Ladipe, and Segun Adeniyi. TRACKA REPORT 2021. BudgIT, 2021. https://budgit.org/wp-content/uploads/2022/12/Trackas-Report.pdf.
Wikipedia
{{cite report |last1=Gheawe |first1=Gabriel |last2=Ievbooje |first2=Uadamen |last3=Adejola |first3=Adewole |last4=Ladipe |first4=Ayomide |last5=Adeniyi |first5=Segun |title=TRACKA REPORT 2021 |publisher=BudgIT |date=2021 |url=https://budgit.org/wp-content/uploads/2022/12/Trackas-Report.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document budgit-000270)}}
BibTeX
@techreport{gheawe2021tracka, author = {Gheawe, Gabriel and Ievbooje, Uadamen and Adejola, Adewole and Ladipe, Ayomide and Adeniyi, Segun}, title = {{TRACKA REPORT 2021}}, institution = {BudgIT}, year = {2021}, url = {https://budgit.org/wp-content/uploads/2022/12/Trackas-Report.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document budgit-000270} }

Full text

Collected · Record updated