The social audit found that the City of Cape Town paid Mshengu Services over R126 million for a service characterized by missing toilets, poor maintenance, and a failure to employ local labour.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The City of Cape Town paid Mshengu Services more than R126 million for temporary toilets, but the audit found 90 toilets missing from the expected 346 in the four audited areas.
  • The distribution of toilets fails to meet the national standard of one toilet per five households; in some areas, more than 10 families share a single toilet, and in one instance, 26 families share one.
  • Maintenance is inadequate, with only 68% of toilets serviced by a Honey Sucker in the week prior to the audit, despite a contractual requirement for servicing three times per week in those areas, and no daily cleaning taking place.
  • A significant portion of the infrastructure is degraded, with 54% of inspected toilets in an unusable state and 66% found to be damaged.
  • Contrary to contract requirements for securing toilets to the ground to prevent toppling, the audit found that no toilets were secured in any of the audited areas, including sandy regions.
  • The contractor failed to employ Community Liaison Officers (CLOs) or local labour from the informal settlements, both of which were requirements of the contract and EPWP guidelines.
  • There is a massive discrepancy in waste disposal records, with approximately 2,997,470 litres of waste unaccounted for based on SJC estimates of expected waste volume versus recorded deposits at Borchards Quarry for February 2013.

Cite the original document

APA
Heinrich Böll Stiftung Southern Africa (2013). REPORT OF THE KHAYELITSHA ‘MSHENGU’ TOILET SOCIAL AUDIT 22-27 APRIL 2013. https://za.boell.org/sites/default/files/uploads/2013/05/sjc_report_of_the_khayelitsha_mshengu_toilet_social_audit.pdf
Chicago
Heinrich Böll Stiftung Southern Africa. REPORT OF THE KHAYELITSHA ‘MSHENGU’ TOILET SOCIAL AUDIT 22-27 APRIL 2013. 2013. https://za.boell.org/sites/default/files/uploads/2013/05/sjc_report_of_the_khayelitsha_mshengu_toilet_social_audit.pdf.
Wikipedia
{{cite report |author=Heinrich Böll Stiftung Southern Africa |title=REPORT OF THE KHAYELITSHA ‘MSHENGU’ TOILET SOCIAL AUDIT 22-27 APRIL 2013 |date=10 May 2013 |url=https://za.boell.org/sites/default/files/uploads/2013/05/sjc_report_of_the_khayelitsha_mshengu_toilet_social_audit.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document boellza-000168)}}
BibTeX
@techreport{heinrichbllstiftungsouthernafrica2013report, author = {{Heinrich Böll Stiftung Southern Africa}}, title = {{REPORT OF THE KHAYELITSHA ‘MSHENGU’ TOILET SOCIAL AUDIT 22-27 APRIL 2013}}, institution = {Heinrich Böll Stiftung Southern Africa}, year = {2013}, month = may, url = {https://za.boell.org/sites/default/files/uploads/2013/05/sjc_report_of_the_khayelitsha_mshengu_toilet_social_audit.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document boellza-000168} }

Full text

Collected · Record updated