Negara Harus Selamatkan PLN dengan Segera Menghentikan Proyek Listrik 35.000 Megawatt
Summary
The document highlights a severe financial crisis at PLN, characterized by a 38 trillion rupiah loss in Q1 2020 and 500 trillion rupiah in debt linked to the 35,000 MW infrastructure project. It argues that the Java-Bali system is suffering from oversupply due to overestimated economic growth and electricity demand projections. The text calls for the government to stop new coal-fired power plant projects, such as PLTU Jawa 9 & 10, to prevent further losses and environmental damage.
Key insights
- PLN is facing a significant financial crisis, reporting a loss of 38 trillion rupiah in the first quarter of 2020 and carrying debts of 500 trillion rupiah, which were used to fund the 35,000 MW electricity infrastructure megaprogram.
- The Java-Bali electricity system is experiencing oversupply because national economic growth targets used for projections were not met; for example, the 2019 RUPTL assumed 5.5 percent growth, while the actual achievement was 5.02 percent.
- An IESR study indicates that demand projections for the Sumatra and Java-Bali regions were 20-50 percent higher than the actual electricity growth trends observed over the last decade.
- The proposed PLTU Jawa 9 & 10 project in Cilegon, Banten, is described as business-unprofitable according to a Korea Development Institute (KDI) pre-feasibility study, showing a negative profitability index and the potential to become a stranded asset.
- Trend Asia warns that continuing new projects amidst market uncertainty could increase PLN's debt burden to 600 trillion rupiah, an amount equivalent to one-quarter of the 2020 state budget (APBN).
Cite the original document
- APA
- TrendAsia (2020). Negara Harus Selamatkan PLN dengan Segera Menghentikan Proyek Listrik 35.000 Megawatt. Trend Asia. https://trendasia.org/negara-harus-selamatkan-pln-dengan-segera-menghentikan-proyek-listrik-35-000-megawatt/
- Chicago
- TrendAsia. Negara Harus Selamatkan PLN dengan Segera Menghentikan Proyek Listrik 35.000 Megawatt. Trend Asia, 2020. https://trendasia.org/negara-harus-selamatkan-pln-dengan-segera-menghentikan-proyek-listrik-35-000-megawatt/.
- Wikipedia
- {{cite press release |last1=TrendAsia |title=Negara Harus Selamatkan PLN dengan Segera Menghentikan Proyek Listrik 35.000 Megawatt |publisher=Trend Asia |date=6 October 2020 |url=https://trendasia.org/negara-harus-selamatkan-pln-dengan-segera-menghentikan-proyek-listrik-35-000-megawatt/ |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @misc{trendasia2020negara, author = {TrendAsia}, title = {{Negara Harus Selamatkan PLN dengan Segera Menghentikan Proyek Listrik 35.000 Megawatt}}, publisher = {Trend Asia}, year = {2020}, month = oct, url = {https://trendasia.org/negara-harus-selamatkan-pln-dengan-segera-menghentikan-proyek-listrik-35-000-megawatt/}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }