Komitmen Baru PLN dan JBIC Belum Cukup Perlu Total Hentikan Pendanaan Proyek PLTU Batubara
Summary
Trend Asia and partner organizations criticize PT PLN's commitment to stop coal-fired power plant (PLTU) projects that have not reached financial closing, citing a lack of transparency and the continued risk of projects like PLTU Indramayu 2 and PLTU Tanjung Jati A. The statement also condemns the Japan Bank for International Cooperation (JBIC) for its role in funding the Cirebon 2 expansion, arguing that JBIC's pledge to exit coal is too late and should include stopping disbursements for ongoing projects to align with the Paris Agreement.
Key insights
- PT PLN (Persero) has begun stopping contracts for coal-fired power plant (PLTU) projects that have not reached the financial closing stage, but the company has not provided detailed information on which specific projects will be halted.
- Specific coal projects in West Java that have not reached financial closing include PLTU Indramayu 2 (1×1000 MW) and PLTU Tanjung Jati A (2×660 MW) in Cirebon; these projects are criticized for causing land conversion and loss of livelihoods for hundreds of farm and salt pond workers.
- The continued construction of coal plants is deemed unnecessary due to electricity overcapacity, which is contributing to the financial waste of PT PLN.
- The Japan Bank for International Cooperation (JBIC) announced its withdrawal from coal business financing, but critics argue this is too late as it follows the funding of the Cirebon 2 expansion (1×1000 MW) and does not include stopping funds for ongoing projects.
Cite the original document
- APA
- TrendAsia (2021). Komitmen Baru PLN dan JBIC Belum Cukup Perlu Total Hentikan Pendanaan Proyek PLTU Batubara. Trend Asia. https://trendasia.org/komitmen-baru-pln-dan-jbic-belum-cukup-perlu-total-hentikan-pendanaan-proyek-pltu-batubara/
- Chicago
- TrendAsia. Komitmen Baru PLN dan JBIC Belum Cukup Perlu Total Hentikan Pendanaan Proyek PLTU Batubara. Trend Asia, 2021. https://trendasia.org/komitmen-baru-pln-dan-jbic-belum-cukup-perlu-total-hentikan-pendanaan-proyek-pltu-batubara/.
- Wikipedia
- {{cite press release |last1=TrendAsia |title=Komitmen Baru PLN dan JBIC Belum Cukup Perlu Total Hentikan Pendanaan Proyek PLTU Batubara |publisher=Trend Asia |date=10 March 2021 |url=https://trendasia.org/komitmen-baru-pln-dan-jbic-belum-cukup-perlu-total-hentikan-pendanaan-proyek-pltu-batubara/ |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @misc{trendasia2021komitmen, author = {TrendAsia}, title = {{Komitmen Baru PLN dan JBIC Belum Cukup Perlu Total Hentikan Pendanaan Proyek PLTU Batubara}}, publisher = {Trend Asia}, year = {2021}, month = mar, url = {https://trendasia.org/komitmen-baru-pln-dan-jbic-belum-cukup-perlu-total-hentikan-pendanaan-proyek-pltu-batubara/}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated