Cegasa – High Energy Storage System for a Mini Hybrid PV Solar Power Plant (Benin)
Summary
The project in Malenville, Benin, involves a 450 kWp roof-mounted photovoltaic solar power plant integrated with a Cegasa High Energy Storage solution. The system utilizes lithium LFP batteries with a storage capacity of 484 kWh (672 Vdc) to ensure a reliable power supply for the Juxtaposed Control Stations at the Benin-Niger border post, addressing the challenges of an underdeveloped local grid.
Key insights
- The installation in Malenville, Benin, consists of a 450 kWp roof-mounted photovoltaic solar power plant and a Cegasa lithium LFP battery backup system with a storage capacity of 484 kWh (672 Vdc).
- The primary objective of the system is to provide a guaranteed power supply and energy backup for the Juxtaposed Control Stations at the border post between Benin and Niger, where the existing grid is described as very underdeveloped.
Cite the original document
- APA
- Alliance for Renewable Electrification (2021). Cegasa – High Energy Storage System for a Mini Hybrid PV Solar Power Plant (Benin). https://renewelec.org/case-study/cegasa-high-energy-storage-system-mini-hybrid-pv-solar-power-plant-benin/
- Chicago
- Alliance for Renewable Electrification. Cegasa – High Energy Storage System for a Mini Hybrid PV Solar Power Plant (Benin). 2021. https://renewelec.org/case-study/cegasa-high-energy-storage-system-mini-hybrid-pv-solar-power-plant-benin/.
- Wikipedia
- {{cite report |author=Alliance for Renewable Electrification |title=Cegasa – High Energy Storage System for a Mini Hybrid PV Solar Power Plant (Benin) |date=15 March 2021 |url=https://renewelec.org/case-study/cegasa-high-energy-storage-system-mini-hybrid-pv-solar-power-plant-benin/ |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @techreport{allianceforrenewableelectrification2021cegasa, author = {{Alliance for Renewable Electrification}}, title = {{Cegasa – High Energy Storage System for a Mini Hybrid PV Solar Power Plant (Benin)}}, institution = {Alliance for Renewable Electrification}, year = {2021}, month = mar, url = {https://renewelec.org/case-study/cegasa-high-energy-storage-system-mini-hybrid-pv-solar-power-plant-benin/}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }