GETting Interconnected in PJM
Summary
This report analyzes the potential for Grid-Enhancing Technologies (GETs) to accelerate and reduce the cost of interconnecting new generation and storage projects within the PJM Interconnection, addressing bottlenecks caused by an aging grid and rising electricity demand.
Key insights
- The implementation of Grid-Enhancing Technologies (GETs) has the potential to allow 6.6 GW of new storage, wind, and solar projects to interconnect by the year 2027.
- GETs offer a significantly more affordable alternative compared to the standard network upgrades that customers seeking interconnection typically encounter.
- The combination of GETs and the new generation they facilitate could result in annual production cost savings of approximately $1 billion throughout the PJM region.
Cite the original document
- APA
- RMI (2024). GETting Interconnected in PJM. https://rmi.org/resources/analyzing-gets-as-a-tool-for-increasing-interconnection-throughput-from-pjms-queue/
- Chicago
- RMI. GETting Interconnected in PJM. 2024. https://rmi.org/resources/analyzing-gets-as-a-tool-for-increasing-interconnection-throughput-from-pjms-queue/.
- Wikipedia
- {{cite report |author=RMI |title=GETting Interconnected in PJM |date=15 February 2024 |url=https://rmi.org/resources/analyzing-gets-as-a-tool-for-increasing-interconnection-throughput-from-pjms-queue/ |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @techreport{rmi2024getting, author = {{RMI}}, title = {{GETting Interconnected in PJM}}, institution = {RMI}, year = {2024}, month = feb, url = {https://rmi.org/resources/analyzing-gets-as-a-tool-for-increasing-interconnection-throughput-from-pjms-queue/}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated