ETUDE TECHNIQUE SUR LE SITE DES PROJETS DE CENTRALE A CHARBON, USINE DE SIDERURGIE TOSYALI ET LE PORT MINERALIER ET VRAQUIER DE BARGNY-MINAM

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The report finds that the Bargny-Sendou area already suffers from severe air pollution, with PM10 levels exceeding national standards by 193% to 540% before the full operation of new industrial projects. It argues that the cumulative impact of the coal plant, mineral port, and steel plant will exacerbate health risks and degrade local resources, including the livelihoods of 1,000 women processing fish at the Khelcom site. The study recommends a strategic environmental assessment of the zone and the conversion of the coal plant to gas.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • Current air quality measurements in the project zone show that PM10 concentrations are significantly above the Senegalese regulatory limit of 150 µg/m3, with measured values ranging from 290 µg/m3 to 810 µg/m3. These exceedances are estimated to be between 193% and 540% relative to national standards.
  • The cumulative impact of the three new projects—the coal power plant, the mineral and bulk port, and the Tosyali steel plant—alongside the existing SOCOCIM cement factory, is expected to be major. All three new projects generate similar types of emissions that will exacerbate the degradation of air quality through direct industrial activity and increased heavy vehicle traffic, including an estimated 200 trucks per day for the steel plant alone.
  • The industrialization of the zone threatens the local economy, particularly the fishing and fish processing sector. The installation of the power plant and the Tosyali steel plant in a Special Economic Zone (ZES) directly threatens the livelihoods of approximately 1,000 women who process fish at the Khelcom site.
  • The mineral and bulk port project involves significant open-air storage of hazardous materials, including 1,446,800 tonnes of coal, 3,090,000 tonnes of phosphate, 600,000 tonnes of sulfur, and 500,000 tonnes of clinker, which the report identifies as a major source of particulate matter pollution.
  • The Tosyali steel plant is expected to have a major impact on air quality. While Phase 1 focuses on recycling scrap and importing billets, Phase 2 will involve producing coke from coal to process iron from Falémé, which will significantly increase emissions of particles and gases such as NH3, H2S, and ZnO.
  • The coal-fired power plant, which has been out of service since July 2019, is identified as a source of ecological and health danger. The report suggests a technical alternative to convert the facility into a gas-fired plant, noting that gas is approximately 30% less polluting than coal.
  • The project area faces severe land-use constraints and 'encirclement.' The town of Bargny, with a population of 60,000, has only 1,500 hectares of inhabited land, while the various industrial projects occupy 4,000 hectares, displacing agriculture and housing.
  • The report highlights a critical water stress issue. The coal plant and steel plant require an estimated 10,000 m3 of potable water per day, whereas the local population of Bargny requires 1,500 m3/day, which is not always fully available.

Cite the original document

APA
THIOUNE, O. (2021). ETUDE TECHNIQUE SUR LE SITE DES PROJETS DE CENTRALE A CHARBON, USINE DE SIDERURGIE TOSYALI ET LE PORT MINERALIER ET VRAQUIER DE BARGNY-MINAM. Natural Justice. https://naturaljustice.org/wp-content/uploads/2023/02/Rapport-final-etude-impacts-cumulatifs-Bargny-15_10_2021.pdf
Chicago
THIOUNE, Ousmane. ETUDE TECHNIQUE SUR LE SITE DES PROJETS DE CENTRALE A CHARBON, USINE DE SIDERURGIE TOSYALI ET LE PORT MINERALIER ET VRAQUIER DE BARGNY-MINAM. Natural Justice, 2021. https://naturaljustice.org/wp-content/uploads/2023/02/Rapport-final-etude-impacts-cumulatifs-Bargny-15_10_2021.pdf.
Wikipedia
{{cite report |last1=THIOUNE |first1=Ousmane |title=ETUDE TECHNIQUE SUR LE SITE DES PROJETS DE CENTRALE A CHARBON, USINE DE SIDERURGIE TOSYALI ET LE PORT MINERALIER ET VRAQUIER DE BARGNY-MINAM |publisher=Natural Justice |date=October 2021 |url=https://naturaljustice.org/wp-content/uploads/2023/02/Rapport-final-etude-impacts-cumulatifs-Bargny-15_10_2021.pdf |access-date=17 August 2026 |via=Climate Insights Directory}}
BibTeX
@techreport{thioune2021etude, author = {THIOUNE, Ousmane}, title = {{ETUDE TECHNIQUE SUR LE SITE DES PROJETS DE CENTRALE A CHARBON, USINE DE SIDERURGIE TOSYALI ET LE PORT MINERALIER ET VRAQUIER DE BARGNY-MINAM}}, institution = {Natural Justice}, year = {2021}, month = oct, url = {https://naturaljustice.org/wp-content/uploads/2023/02/Rapport-final-etude-impacts-cumulatifs-Bargny-15_10_2021.pdf}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }

Full text

Collected · Record updated