Procédures à suivre pour les projets de construction
Summary
This guide specifies the mandatory documentation and procurement steps for construction projects, most notably requiring three comparative quotes to ensure the rational and economic use of funds.
Key insights
- To ensure funds are used rationally and economically, project implementers should provide three different comparative quotes and justify their choice of contractor, though the cheapest offer is not mandatory if other factors like solidity, solvency, and past competence are considered.
- Project implementers must provide a copy of the contract if professional contractors are used, and any modifications to approved plans require prior notification and a formal waiver.
- The final report must include a timeline of events, a confirmation from an architect or site manager that construction conforms to approved plans, captioned photographs of the buildings, and procurement documents.
- A final account verified by an independent accountant is generally required upon project completion, unless a detailed contract with a general contractor exists, in which case reports from an independent building expert and payment justifications are required instead.
Cite the original document
- APA
- Misereor (n.d.). Procédures à suivre pour les projets de construction. https://www.misereor.org/fileadmin/user_upload_misereororg/cooperation/fr/construction/guide-procedures-a-suivre-pour-projets-de-construction.pdf
- Chicago
- Misereor. Procédures à suivre pour les projets de construction. n.d. https://www.misereor.org/fileadmin/user_upload_misereororg/cooperation/fr/construction/guide-procedures-a-suivre-pour-projets-de-construction.pdf.
- Wikipedia
- {{cite report |author=Misereor |title=Procédures à suivre pour les projets de construction |url=https://www.misereor.org/fileadmin/user_upload_misereororg/cooperation/fr/construction/guide-procedures-a-suivre-pour-projets-de-construction.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document misereor-000145)}}
- BibTeX
- @techreport{misereorndprocdures, author = {{Misereor}}, title = {{Procédures à suivre pour les projets de construction}}, institution = {Misereor}, url = {https://www.misereor.org/fileadmin/user_upload_misereororg/cooperation/fr/construction/guide-procedures-a-suivre-pour-projets-de-construction.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document misereor-000145} }
Full text
Collected · Record updated