Enbridge Should Consider Closing Its Old, Troubled Line 5 Pipeline
Summary
This report concludes that Enbridge's plan to replace segments of the 70-year-old Line 5 pipeline is financially ill-advised, as the tunnel project could cost three or more times its initial estimate while the market for its products declines.
Key insights
- The Enbridge tunnel pipeline project faces significant cost escalation; while the 2018 estimate was $500 million, a 2022 earnings call cited $750 million, and IEEFA estimates the final cost could be $1.5 billion or more due to construction inflation and design changes.
- The tunnel's design was enlarged from a 10-foot to a 21-foot interior diameter, which increases the tunnel's volume by 3.67 times and increases water infiltration management challenges by up to 40%.
- Enbridge faces additional capital costs for a 41.2-mile re-route of Line 5 around the Bad River Reservation in Wisconsin, projected at $450 million in 2024 dollars but likely to reach $500 million or more.
- Continued operation of the old dual pipeline during the tunnel's construction (which may not start operations until at least 2030) poses severe environmental risks, with potential spill damages estimated between $1.37 billion and $45.8 billion depending on the scenario.
- Global and regional demand for Line 5's products is on a declining trajectory due to the energy transition, with the IEA projecting global oil demand could drop to 55 million bpd by 2050 if decarbonization pledges are met.
- Residential propane consumption in the East North Central region of the U.S. is projected to plummet, aided by government rebates for converting homes to electric heat pumps.
- Enbridge's financial profile is described by Moody's as weak, with a senior unsecured rating downgraded to Baa2 in March 2024, and the company's debt-to-EBITDA ratio reported at 4.9x in the third quarter of 2024.
- The report argues that investing in the tunnel and re-route creates 'carbon lock-in,' restricting future flexibility and increasing the costs of achieving climate goals by prolonging fossil fuel infrastructure.
Cite the original document
- APA
- Schlissel, D. (n.d.). Enbridge Should Consider Closing Its Old, Troubled Line 5 Pipeline. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2025-01/Updated%20Authors-Enbridge%20Should%20Consider%20Closing%20Line%205_Report_January%202025_Final.pdf
- Chicago
- Schlissel, David. Enbridge Should Consider Closing Its Old, Troubled Line 5 Pipeline. Institute for Energy Economics and Financial Analysis, n.d. https://ieefa.org/sites/default/files/2025-01/Updated%20Authors-Enbridge%20Should%20Consider%20Closing%20Line%205_Report_January%202025_Final.pdf.
- Wikipedia
- {{cite report |last1=Schlissel |first1=David |title=Enbridge Should Consider Closing Its Old, Troubled Line 5 Pipeline |publisher=Institute for Energy Economics and Financial Analysis |url=https://ieefa.org/sites/default/files/2025-01/Updated%20Authors-Enbridge%20Should%20Consider%20Closing%20Line%205_Report_January%202025_Final.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-002042)}}
- BibTeX
- @techreport{schlisselndenbridge, author = {Schlissel, David}, title = {{Enbridge Should Consider Closing Its Old, Troubled Line 5 Pipeline}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2025-01/Updated%20Authors-Enbridge%20Should%20Consider%20Closing%20Line%205_Report_January%202025_Final.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-002042} }
Full text
Collected · Record updated