Trans Mountain Expansion Pipeline Project (TMX) has Financial Issues Despite Government Bailout
Summary
This IEEFA fact sheet finds that the Canadian government's total taxpayer exposure to the Trans Mountain Expansion Pipeline Project exceeds $40 billion, with construction costs ballooning to 584% above initial estimates.
Key insights
- The Canadian government's direct funding for the Trans Mountain Expansion Pipeline Project (TMX) is $35.6 billion, which is $1.4 billion more than typically reported. When indirect financial subsidies are included, the total taxpayer exposure exceeds $40 billion.
- Final construction costs for the TMX pipeline increased to 584% above the initial budget estimates.
- Of the total funding provided, $26 billion is ineligible for recovery through proposed shipping tolls, and the ability to recoup the remaining investment is threatened by high toll rates.
Cite the original document
- APA
- Institute for Energy Economics and Financial Analysis (n.d.). Trans Mountain Expansion Pipeline Project (TMX) has Financial Issues Despite Government Bailout. https://ieefa.org/sites/default/files/2025-09/TransMountainPipelineFactSheet2025%20%282%29.pdf
- Chicago
- Institute for Energy Economics and Financial Analysis. Trans Mountain Expansion Pipeline Project (TMX) has Financial Issues Despite Government Bailout. n.d. https://ieefa.org/sites/default/files/2025-09/TransMountainPipelineFactSheet2025%20%282%29.pdf.
- Wikipedia
- {{cite report |author=Institute for Energy Economics and Financial Analysis |title=Trans Mountain Expansion Pipeline Project (TMX) has Financial Issues Despite Government Bailout |url=https://ieefa.org/sites/default/files/2025-09/TransMountainPipelineFactSheet2025%20%282%29.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-002027)}}
- BibTeX
- @techreport{instituteforenergyeconomicsandfinancialanalysisndtrans, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{Trans Mountain Expansion Pipeline Project (TMX) has Financial Issues Despite Government Bailout}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2025-09/TransMountainPipelineFactSheet2025%20%282%29.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-002027} }
Full text
Collected · Record updated