It’s Time to Retire, Not Bail Out, OVEC’s Aging and Expensive Coal Plants
Summary
The report concludes that Indiana's HB 1414 will cost electricity customers at least $128 million through 2026 to maintain two aging coal plants that are no longer economically viable or necessary for grid reliability.
Key insights
- Indiana electricity customers of Indiana Michigan Power Company (I&M) and Vectren could pay at least $128 million above the cost of market power to keep the Kyger Creek and Clifty Creek plants in service between 2020 and 2026.
- The cost of power from the Ohio Valley Electric Corporation (OVEC) increased by nearly 60 percent from 2007 to 2018, driven by declining generation and over $1.6 billion in capital expenditures since 2003, including $1 billion for flue gas desulfurization scrubbers between 2011 and 2013.
- Low natural gas prices since 2008/2009 have undermined the plants' viability by lowering energy market prices and displacing coal generation, leading to a decline in total OVEC generation of more than 25% between 2007 and 2019.
- The Kyger Creek and Clifty Creek plants are not required for grid reliability, as PJM's 2021/2022 capacity auction showed a 21.5% reserve margin, which is 5.7% above the target of 15.8%.
- The description of the plants as 'national security resources' is inaccurate because the Portsmouth Uranium Enrichment Facility they were built to serve closed in 2002, and the supply contract was cancelled in 2003.
- HB 1414 creates regulatory roadblocks to retiring coal plants and allows utilities to recover costs for 'legacy generation resources' through fuel adjustment charges, transferring financial risk from owners to customers.
Cite the original document
- APA
- Schlissel, D. (2020). It’s Time to Retire, Not Bail Out, OVEC’s Aging and Expensive Coal Plants. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/Time-to-Retire-OVECs-Aging-and-Expensive-Coal-Plants_April-2020.pdf
- Chicago
- Schlissel, David. It’s Time to Retire, Not Bail Out, OVEC’s Aging and Expensive Coal Plants. Institute for Energy Economics and Financial Analysis, 2020. https://ieefa.org/sites/default/files/resources/Time-to-Retire-OVECs-Aging-and-Expensive-Coal-Plants_April-2020.pdf.
- Wikipedia
- {{cite report |last1=Schlissel |first1=David |title=It’s Time to Retire, Not Bail Out, OVEC’s Aging and Expensive Coal Plants |publisher=Institute for Energy Economics and Financial Analysis |date=March 2020 |url=https://ieefa.org/sites/default/files/resources/Time-to-Retire-OVECs-Aging-and-Expensive-Coal-Plants_April-2020.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-002014)}}
- BibTeX
- @techreport{schlissel2020its, author = {Schlissel, David}, title = {{It’s Time to Retire, Not Bail Out, OVEC’s Aging and Expensive Coal Plants}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2020}, month = mar, url = {https://ieefa.org/sites/default/files/resources/Time-to-Retire-OVECs-Aging-and-Expensive-Coal-Plants_April-2020.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-002014} }
Full text
Collected · Record updated