Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The Vogtle Nuclear Project Units 3 and 4 are at least six years behind schedule with total costs expected to exceed $30 billion, making the resulting power approximately five times more expensive than solar plus storage alternatives.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The total cost of the Vogtle project, including financing, rose from an estimated $14.1 billion in 2009 to approximately $32 billion in the fall of 2021, representing an approximate 127% increase.
  • Commercial operation for the two units is now estimated for 2022 and 2023, which is more than six years behind the original projected dates of April 2016 and April 2017.
  • Georgia Power's forecasts for the commercial operation dates have been described by the commission staff team as "unrealistic and unreliable," leading to a culture of production over quality and extensive rework.
  • Between January 2011 and December 2020, Georgia Power customers paid over $3.5 billion in financing costs via a bill rider, with residential customers bearing 47% and commercial customers 40% of that burden, while industrial customers paid only 11%.
  • The estimated cost of power from the new reactors is $150 per megawatt-hour (MWh), which is approximately five times the $30.19 per MWh average price of recent solar plus storage purchase power agreements signed by Georgia Power.
  • The total revenue requirements for Vogtle 3 and 4 are expected to exceed $70 billion over their 60-year operating lives, significantly exceeding the costs of natural gas combined cycle units under all analyzed price scenarios.

Cite the original document

APA
Schlissel, D. (2022). Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf
Chicago
Schlissel, David. Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule. Institute for Energy Economics and Financial Analysis, 2022. https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf.
Wikipedia
{{cite report |last1=Schlissel |first1=David |title=Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule |publisher=Institute for Energy Economics and Financial Analysis |date=January 2022 |url=https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001952)}}
BibTeX
@techreport{schlissel2022southern, author = {Schlissel, David}, title = {{Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than \$30 Billion and Are at Least Six Years Behind Schedule}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2022}, month = jan, url = {https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001952} }

Full text

Collected · Record updated