Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule
Summary
The Vogtle Nuclear Project Units 3 and 4 are at least six years behind schedule with total costs expected to exceed $30 billion, making the resulting power approximately five times more expensive than solar plus storage alternatives.
Key insights
- The total cost of the Vogtle project, including financing, rose from an estimated $14.1 billion in 2009 to approximately $32 billion in the fall of 2021, representing an approximate 127% increase.
- Commercial operation for the two units is now estimated for 2022 and 2023, which is more than six years behind the original projected dates of April 2016 and April 2017.
- Georgia Power's forecasts for the commercial operation dates have been described by the commission staff team as "unrealistic and unreliable," leading to a culture of production over quality and extensive rework.
- Between January 2011 and December 2020, Georgia Power customers paid over $3.5 billion in financing costs via a bill rider, with residential customers bearing 47% and commercial customers 40% of that burden, while industrial customers paid only 11%.
- The estimated cost of power from the new reactors is $150 per megawatt-hour (MWh), which is approximately five times the $30.19 per MWh average price of recent solar plus storage purchase power agreements signed by Georgia Power.
- The total revenue requirements for Vogtle 3 and 4 are expected to exceed $70 billion over their 60-year operating lives, significantly exceeding the costs of natural gas combined cycle units under all analyzed price scenarios.
Cite the original document
- APA
- Schlissel, D. (2022). Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf
- Chicago
- Schlissel, David. Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule. Institute for Energy Economics and Financial Analysis, 2022. https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf.
- Wikipedia
- {{cite report |last1=Schlissel |first1=David |title=Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than $30 Billion and Are at Least Six Years Behind Schedule |publisher=Institute for Energy Economics and Financial Analysis |date=January 2022 |url=https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001952)}}
- BibTeX
- @techreport{schlissel2022southern, author = {Schlissel, David}, title = {{Southern Company’s Troubled Vogtle Nuclear Project Units 3 and 4 Now Expected to Cost More Than \$30 Billion and Are at Least Six Years Behind Schedule}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2022}, month = jan, url = {https://ieefa.org/sites/default/files/resources/Southern-Companys-Troubled-Vogtle-Nuclear-Project_January-2022.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001952} }
Full text
Collected · Record updated