The report finds that since taking over on June 1, 2021, LUMA Energy has presided over a decline in service quality in Puerto Rico, characterized by longer outage restoration times and increased customer complaints. IEEFA attributes these failures to a critical shortage of experienced personnel—as LUMA hired fewer than 30% of former PREPA workers—and a contract that lacks transparency, effective oversight, and incentives for meeting renewable energy or financial goals. The document further criticizes the opaque procurement process used to select LUMA and the FOMB's failure to implement contracting reforms, noting that the privatization has created an additional annual labor cost of approximately $230 million for the commonwealth government.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • Service quality for Puerto Rican customers declined following LUMA Energy's takeover on June 1, 2021, with reports of longer outage restoration times, voltage fluctuations, and a doubling of monthly complaints to the Independent Consumer Protection Office compared to the PREPA era.
  • LUMA's operational failures are linked to a severe shortage of experienced staff; the company hired fewer than 30% of former Puerto Rico Electric Power Authority (PREPA) workers and operated with roughly 60% of the workforce previously used for the same tasks.
  • The privatization has imposed a significant financial burden on the bankrupt commonwealth government, including an estimated $230 million in annual costs to maintain the salaries and benefits of transferred PREPA employees and a one-time unbudgeted expense of $750 million for reserve accounts.
  • The contract is characterized by a lack of transparency and weak oversight; LUMA has refused to provide requested data to the Puerto Rico House of Representatives, and the P3 Authority's oversight is described as "passive" compared to the Puerto Rico Energy Bureau (PREB).
  • The LUMA contract lacks mechanisms to ensure the island's long-term energy goals are met, containing no financial incentives or penalties for integrating renewable energy or achieving electricity rates of 20 cents per kilowatt-hour or less.
  • The procurement process for selecting LUMA was opaque and lacked independence, with evidence that four of five committee members submitted nearly identical scores and some financial metrics appeared to be copied directly from a consultant's report.
  • The Financial Oversight and Management Board (FOMB) has failed in its mandate to reform government contracting, aggressively defending the LUMA contract despite its labor and oversight deficiencies and the lack of analysis supporting claims of reduced costs.

Cite the original document

APA
Kunkel, C., & Sanzillo, T. (2021). Puerto Rico Grid Privatization Flaws Highlighted in First Two Months of Operation. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/Puerto-Rico-Grid-Privatization-Flaws-Highlighted-in-First-Two-Months-of-Operation_August-2021.pdf
Chicago
Kunkel, Cathy, and Tom Sanzillo. Puerto Rico Grid Privatization Flaws Highlighted in First Two Months of Operation. Institute for Energy Economics and Financial Analysis, 2021. https://ieefa.org/sites/default/files/resources/Puerto-Rico-Grid-Privatization-Flaws-Highlighted-in-First-Two-Months-of-Operation_August-2021.pdf.
Wikipedia
{{cite report |last1=Kunkel |first1=Cathy |last2=Sanzillo |first2=Tom |title=Puerto Rico Grid Privatization Flaws Highlighted in First Two Months of Operation |publisher=Institute for Energy Economics and Financial Analysis |date=August 2021 |url=https://ieefa.org/sites/default/files/resources/Puerto-Rico-Grid-Privatization-Flaws-Highlighted-in-First-Two-Months-of-Operation_August-2021.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001853)}}
BibTeX
@techreport{kunkel2021puerto, author = {Kunkel, Cathy and Sanzillo, Tom}, title = {{Puerto Rico Grid Privatization Flaws Highlighted in First Two Months of Operation}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2021}, month = aug, url = {https://ieefa.org/sites/default/files/resources/Puerto-Rico-Grid-Privatization-Flaws-Highlighted-in-First-Two-Months-of-Operation_August-2021.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001853} }

Full text

Collected · Record updated