The Prairie State Coal Plant: The Reality vs. the Promise
Summary
The report finds that the Prairie State coal plant's first-year power costs are 40% to 100% higher than promised, creating significant long-term fiscal stress for participating communities.
Key insights
- The first-year cost of power from the Prairie State Energy Campus is 40% to 100% higher than the $41 per megawatt hour promised to participating communities in 2007.
- Power costs from the plant are significantly higher than the wholesale prices in the PJM and MISO markets and are expected to remain so for at least a decade.
- The increase in power costs is a direct result of construction costs rising from an initial estimate of $4.0 billion to $4.9 billion.
- Participating communities are unlikely to see a cumulative annual economic benefit from the project until the late 2030s or 2040s.
- The Lively Grove Mine may lack the capacity to provide the promised 30-year coal supply, potentially forcing owners to purchase more expensive fuel and continue debt service after the mine closes.
- The Jordan Grove ashfill site has significantly less capacity than originally permitted, with only 12-14 years of capacity instead of the promised 23 years.
- Approximately 82 communities are at heightened risk because they signed 'take-or-pay' contracts, obligating them to pay fixed costs regardless of whether the plant generates power.
- The plant's projected 85% annual capacity factor is considered overly optimistic, and a lower factor (e.g., 75%) would further increase the average power cost to $80.67 per MWh.
- Market competition from shale-derived natural gas and wind generation is expected to keep wholesale electricity prices low, further delaying the point at which the plant's power becomes competitive.
Cite the original document
- APA
- Sanzillo, T., Hamilton, L., & Schlissel, D. (2012). The Prairie State Coal Plant: The Reality vs. the Promise. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2022-04/Prairie%20State%20Report.pdf
- Chicago
- Sanzillo, Tom, Lisa Hamilton, and David Schlissel. The Prairie State Coal Plant: The Reality vs. the Promise. Institute for Energy Economics and Financial Analysis, 2012. https://ieefa.org/sites/default/files/2022-04/Prairie%20State%20Report.pdf.
- Wikipedia
- {{cite report |last1=Sanzillo |first1=Tom |last2=Hamilton |first2=Lisa |last3=Schlissel |first3=David |title=The Prairie State Coal Plant: The Reality vs. the Promise |publisher=Institute for Energy Economics and Financial Analysis |date=29 August 2012 |url=https://ieefa.org/sites/default/files/2022-04/Prairie%20State%20Report.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001831)}}
- BibTeX
- @techreport{sanzillo2012prairie, author = {Sanzillo, Tom and Hamilton, Lisa and Schlissel, David}, title = {{The Prairie State Coal Plant: The Reality vs. the Promise}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2012}, month = aug, url = {https://ieefa.org/sites/default/files/2022-04/Prairie%20State%20Report.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001831} }
Full text
Collected · Record updated