The Kemper IGCC Project: Cost and Schedule Risks
Summary
The report finds that the Kemper IGCC project is only 40-45% complete and faces substantial cost and schedule risks due to the use of untested commercial-scale technologies, contradicting the Mississippi Power Company's claims of being 70% complete.
Key insights
- The Kemper project's actual completion status is approximately 40-45%, contradicting the Mississippi Power Company's (MPC) claim that it is more than 70% complete.
- Direct construction costs for the Kemper project have increased by more than 20% from the original estimate of $2.3953 billion presented in late 2009/early 2010.
- Uncapped costs, including the mine, CO2 pipeline, and financing costs, have increased by approximately $270 million, or more than 50%, since the project's certification in 2010.
- The project is behind schedule, with engineering and construction lagging behind planned targets as of July 2012; for example, concrete foundations work was 23 percentage points behind plan.
- The use of untested commercial-scale technologies, specifically the TRIG gasification technology and CO2 capture processes, creates a substantial risk of further schedule delays and cost increases.
- Experience from the Edwardsport IGCC project in Indiana shows that similar first-of-a-kind plants face significant delays during commissioning and testing, with Edwardsport's in-service date slipping by eight months.
- The economic viability analysis provided by MPC is questioned because it relies on natural gas price projections that are significantly higher than current futures prices and ignores excess capacity costs.
Cite the original document
- APA
- Schlissel, D. (2012). The Kemper IGCC Project: Cost and Schedule Risks. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/Kemper-IGCC-Project-Cost-and-Schedule-Risk-Report.pdf
- Chicago
- Schlissel, David. The Kemper IGCC Project: Cost and Schedule Risks. Institute for Energy Economics and Financial Analysis, 2012. https://ieefa.org/sites/default/files/resources/Kemper-IGCC-Project-Cost-and-Schedule-Risk-Report.pdf.
- Wikipedia
- {{cite report |last1=Schlissel |first1=David |title=The Kemper IGCC Project: Cost and Schedule Risks |publisher=Institute for Energy Economics and Financial Analysis |date=19 November 2012 |url=https://ieefa.org/sites/default/files/resources/Kemper-IGCC-Project-Cost-and-Schedule-Risk-Report.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001675)}}
- BibTeX
- @techreport{schlissel2012kemper, author = {Schlissel, David}, title = {{The Kemper IGCC Project: Cost and Schedule Risks}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2012}, month = nov, url = {https://ieefa.org/sites/default/files/resources/Kemper-IGCC-Project-Cost-and-Schedule-Risk-Report.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001675} }
Full text
Collected · Record updated