Material Risks: How public accountability is slowing tar sands development
Summary
This report argues that public opposition to pipeline infrastructure, combined with falling oil prices, has created a 'carbon blockade' that is making tar sands investments financially precarious. A key finding is that public accountability campaigns contributed to $17.1 billion in lost revenues for tar sands producers between 2010 and 2013.
Key insights
- Public accountability efforts, specifically pipeline campaigns, played a significant role in the 2014 cancellation of three major tar sands projects: Shell’s Pierre River, Total’s Joslyn North, and Statoil’s Corner Project.
- The three cancelled projects in 2014 would have produced 4.7 billion barrels of bitumen and released 2.8 billion metric tonnes of CO2, which is equivalent to the annual emissions of 735 coal plants.
- Between 2010 and 2013, tar sands producers lost $30.9 billion due to price differentials caused by transportation bottlenecks and tight oil fields; 55 percent ($17.1 billion) of this is attributed to public accountability campaigns.
- Nine out of the ten leading tar sands producers in Canada underperformed the stock market over the five years preceding the report.
- Capital expenditure (Capex) in the tar sands peaked in 2012 at $27.2 billion CAD and has since declined, with a forecast suggesting it will not return to 2014 levels for at least 15 years.
- A forecast model suggests that if no new major pipelines are built, up to 6.9 billion barrels of tar sands oil could remain underground by 2030, avoiding 4.1 billion tonnes of CO2 emissions.
- The Alberta tar sands contain a high concentration of 'stranded assets'; over 40 percent of the $1.2 trillion in global oil investment at risk of becoming stranded if climate targets are met is concentrated there.
- Rail transport is an insufficient alternative to pipelines because it is more expensive, vulnerable to weather and congestion, and cannot profitably handle the projected 4 million bpd capacity of proposed pipelines.
Cite the original document
- APA
- Sanzillo, T., Stockman, L., Rogers, D., McKinnon, H., Bast, E., & Kretzmann, S. (2014). Material Risks: How public accountability is slowing tar sands development. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/IEEFA.OCI_.Material-Risks.compressed.pdf
- Chicago
- Sanzillo, Tom, Lorne Stockman, Deborah Rogers, Hannah McKinnon, Elizabeth Bast, and Steve Kretzmann. Material Risks: How public accountability is slowing tar sands development. Institute for Energy Economics and Financial Analysis, 2014. https://ieefa.org/sites/default/files/resources/IEEFA.OCI_.Material-Risks.compressed.pdf.
- Wikipedia
- {{cite report |last1=Sanzillo |first1=Tom |last2=Stockman |first2=Lorne |last3=Rogers |first3=Deborah |last4=McKinnon |first4=Hannah |last5=Bast |first5=Elizabeth |last6=Kretzmann |first6=Steve |title=Material Risks: How public accountability is slowing tar sands development |publisher=Institute for Energy Economics and Financial Analysis |date=October 2014 |url=https://ieefa.org/sites/default/files/resources/IEEFA.OCI_.Material-Risks.compressed.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001533)}}
- BibTeX
- @techreport{sanzillo2014material, author = {Sanzillo, Tom and Stockman, Lorne and Rogers, Deborah and McKinnon, Hannah and Bast, Elizabeth and Kretzmann, Steve}, title = {{Material Risks: How public accountability is slowing tar sands development}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2014}, month = oct, url = {https://ieefa.org/sites/default/files/resources/IEEFA.OCI_.Material-Risks.compressed.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001533} }