Queensland's Financial Provisioning Scheme review
Summary
IEEFA argues that Queensland's Financial Provisioning Scheme fails to manage systemic risk from sector concentration, particularly in coal, and recommends introducing portfolio-based risk management and stricter triggers for surety recalculation.
Key insights
- The Financial Provisioning Scheme (FPS) does not currently account for systemic risk where multiple mining companies in the same sector fail simultaneously, which is a significant concern given that coalmining accounts for approximately 70% of the aggregate estimated rehabilitation cost (ERC).
- Coalmining represents a higher risk than other commodities in the Scheme, as it accounts for 77% of Fund contributions despite representing 58% of the ERCs covered under the Scheme.
- The abandonment of the Bluff open-cut coalmine serves as a cautionary tale, as it is the first open-cut coalmine in Queensland history where the liability for closure and environmental management has shifted to the state.
- The removal of the mandatory three-yearly audit of Progressive Rehabilitation Completion Plans (PRCPs) by the 2025 Amendment Bill is considered premature, as 64% of coalmining PRCPs are less than a year old and their effectiveness remains untested.
- Current estimated rehabilitation costs (ERC) in Queensland include a 10% general project contingency, but this is insufficient to cover specific climate-related risks such as major flooding or reduced vegetation success due to heatwaves.
- IEEFA recommends that insolvency, administration, or liquidation of an Environmental Authority holder or its parent entity should automatically trigger an immediate risk reassessment and a recalculation of surety to the full ERC.
Cite the original document
- APA
- Gorringe, A. (2026). Queensland's Financial Provisioning Scheme review. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2026-10/IEEFA%20submission_%20FPSreview.pdf
- Chicago
- Gorringe, Andrew. Queensland's Financial Provisioning Scheme review. Institute for Energy Economics and Financial Analysis, 2026. https://ieefa.org/sites/default/files/2026-10/IEEFA%20submission_%20FPSreview.pdf.
- Wikipedia
- {{cite press release |last1=Gorringe |first1=Andrew |title=Queensland's Financial Provisioning Scheme review |publisher=Institute for Energy Economics and Financial Analysis |date=30 September 2026 |url=https://ieefa.org/sites/default/files/2026-10/IEEFA%20submission_%20FPSreview.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001455)}}
- BibTeX
- @misc{gorringe2026queenslands, author = {Gorringe, Andrew}, title = {{Queensland's Financial Provisioning Scheme review}}, publisher = {Institute for Energy Economics and Financial Analysis}, year = {2026}, month = sep, url = {https://ieefa.org/sites/default/files/2026-10/IEEFA%20submission_%20FPSreview.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001455} }
Full text
Collected · Record updated