A global shortage of heavy-duty gas turbines, with delivery timelines extending to eight years, is significantly delaying LNG-to-power projects in Vietnam and the Philippines. This bottleneck, combined with regulatory and financial hurdles, makes these projects less competitive compared to rapidly growing low-cost renewables and battery storage.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The three largest gas turbine manufacturers—GE Vernova, Siemens Energy, and Mitsubishi Heavy Industries (MHI)—control approximately 90% of the global market for turbines over 100MW and are currently reporting extensive backlogs, advising developers to plan for procurement timelines of seven to eight years.
  • Vietnam is projected to miss its 2030 targets for domestic gas and LNG-fired power capacity by a total of 25.2 GW, with 19.7 GW of the shortfall attributed to LNG-fired capacity and 5.5 GW to domestic gas-to-power capacity.
  • The Philippines is unlikely to bring any new LNG-fired power plants online this decade beyond one project expected to begin fully operating in 2025; the remaining 10.7 GW pipeline of proposed projects remains in early development and lacks secured turbine orders.
  • Capital costs for gas turbines have increased nearly threefold over the last two years, rising from USD 700–1,000 per kW to an estimated USD 2,400 per kW, with manufacturers now charging non-refundable reservation fees.
  • Turbine manufacturers are reluctant to rapidly expand capacity due to risks of over-investment, citing past market collapses in 2002, 2010, and 2017–2018, and concerns that current demand driven by AI and data centers may be inflated.
  • Project delays for LNG-to-power in Southeast Asia are creating opportunities for the expansion of renewables and battery storage, which have shorter development timelines and falling costs.

Cite the original document

APA
Reynolds, S. (n.d.). Global gas turbine shortages add to LNG challenges in Vietnam and the Philippines. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2025-10/IEEFA%20Report_Global%20gas%20turbine%20shortages%20add%20to%20LNG%20challenges%20in%20Vietnam%20and%20the%20Philippines_October2025.pdf
Chicago
Reynolds, Sam. Global gas turbine shortages add to LNG challenges in Vietnam and the Philippines. Institute for Energy Economics and Financial Analysis, n.d. https://ieefa.org/sites/default/files/2025-10/IEEFA%20Report_Global%20gas%20turbine%20shortages%20add%20to%20LNG%20challenges%20in%20Vietnam%20and%20the%20Philippines_October2025.pdf.
Wikipedia
{{cite report |last1=Reynolds |first1=Sam |title=Global gas turbine shortages add to LNG challenges in Vietnam and the Philippines |publisher=Institute for Energy Economics and Financial Analysis |url=https://ieefa.org/sites/default/files/2025-10/IEEFA%20Report_Global%20gas%20turbine%20shortages%20add%20to%20LNG%20challenges%20in%20Vietnam%20and%20the%20Philippines_October2025.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001408)}}
BibTeX
@techreport{reynoldsndglobal, author = {Reynolds, Sam}, title = {{Global gas turbine shortages add to LNG challenges in Vietnam and the Philippines}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2025-10/IEEFA%20Report_Global%20gas%20turbine%20shortages%20add%20to%20LNG%20challenges%20in%20Vietnam%20and%20the%20Philippines_October2025.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001408} }

Full text

Collected · Record updated