This report finds that over 50GW of renewable energy capacity is currently stranded across India due to a mismatch between generation readiness and transmission infrastructure availability.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • As of June 2025, more than 50GW of renewable energy capacity is stranded nationwide, which increases per-unit transmission costs and limits the speed of bringing new capacity online.
  • India's transmission expansion is failing to meet National Electricity Plan (NEP) targets; in FY2025, only 8,830ckm of new lines were commissioned against a target of 15,253ckm, representing a 42% shortfall.
  • Significant system inefficiencies exist, with analysis from the National Renewable Energy Laboratory indicating that up to 71% of Inter-State Transmission System (ISTS) corridors operate at less than 30% utilisation.
  • Right-of-way (RoW) disputes and land acquisition are major barriers to timely development; for instance, at least 14 ISTS projects have faced significant delays linked to unresolved RoW issues.
  • In Rajasthan, 8GW of renewable energy capacity is stranded as of July 2025, with nearly half of the solar capacity curtailed during peak hours due to the lack of an Associated Transmission System (ATS).
  • Speculative hoarding of transmission capacity by entities without genuine project intent has created artificial scarcity in corridors like Fatehgarh and Bikaner, driving connectivity premiums up to Rs40 lakh per MW.
  • Technical failures and non-compliance with grid standards cause significant losses; from January to June 2025, the northern region reported over 6,300MW of generation loss linked to grid faults and LVRT/HVRT non-compliance.
  • Equipment procurement is hindered by 2023 General Financial Rules that limit sourcing from neighbouring countries, particularly affecting High Voltage Direct Current (HVDC) systems.

Cite the original document

APA
Institute for Energy Economics and Financial Analysis (n.d.). Green Power Transmission Development in India. https://ieefa.org/sites/default/files/2025-09/Green%20Power%20Transmission%20Development%20in%20India%20FV6%20%281%29.pdf
Chicago
Institute for Energy Economics and Financial Analysis. Green Power Transmission Development in India. n.d. https://ieefa.org/sites/default/files/2025-09/Green%20Power%20Transmission%20Development%20in%20India%20FV6%20%281%29.pdf.
Wikipedia
{{cite report |author=Institute for Energy Economics and Financial Analysis |title=Green Power Transmission Development in India |url=https://ieefa.org/sites/default/files/2025-09/Green%20Power%20Transmission%20Development%20in%20India%20FV6%20%281%29.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001288)}}
BibTeX
@techreport{instituteforenergyeconomicsandfinancialanalysisndgreen, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{Green Power Transmission Development in India}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2025-09/Green%20Power%20Transmission%20Development%20in%20India%20FV6%20%281%29.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001288} }

Full text

Collected · Record updated